249 N LADERA DR 90210
Certificate Information: 249 N LADERA DR 90210
- Application / Permit
- 21014-20000-00194
- Plan Check / Job No.
- B21VN00545
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL & ADDITION OF STUDY ROOM IN THE ATTIC AREA TO (E) SFD
- Permit Issued
- Issued on 6/2/2021
- Issuing Office
- Current Status
- CofO Issued on 10/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2021 | MOHAMMAD ESMAILI |
| Corrections Issued | 1/30/2021 | MOHAMMAD ESMAILI |
| Quality Review Completed | 2/3/2021 | OMID HEDAYAT |
| Applicant returned to address corrections | 6/2/2021 | MOHAMMAD ESMAILI |
| Plan Check Approved | 6/2/2021 | MOHAMMAD ESMAILI |
| Issued | 6/2/2021 | APPLICANT |
| Building Plans Picked Up | 4/15/2022 | APPLICANT |
| CofO in Progress | 9/8/2022 | CHRISTOPHER WILSON |
| CofO in Progress | 9/8/2022 | CHRISTOPHER WILSON |
| Permit Finaled | 10/6/2022 | DANIEL ORRANTE |
| Permit Finaled | 10/6/2022 | DANIEL ORRANTE |
| CofO Issued | 10/6/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZA Case | Cleared | 2/16/2021 | DENZEL HENDERSON |
| ZA Case | Cleared | 2/16/2021 | DENZEL HENDERSON |
| BHO/Hillside ordinance | Cleared | 2/23/2021 | SAUL GARCIA |
| BHO/Hillside ordinance | Cleared | 2/23/2021 | SAUL GARCIA |
| BHO/Hillside ordinance | Cleared | 2/23/2021 | SAUL GARCIA |
| BHO/Hillside ordinance | Cleared | 2/23/2021 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 2/23/2021 | SAUL GARCIA |
| BHO/Hillside ordinance | Cleared | 2/24/2021 | HISASHI KOBAYAKAWA |
| Distance to fire station | Cleared | 4/6/2021 | KURT CORRAL |
| Hydrant and Access approval | Cleared | 4/6/2021 | KURT CORRAL |
| GPI Written Notices | Cleared | 6/2/2021 | MOHAMMAD ESMAILI |
| Grading Pre-Inspection | Cleared | 6/2/2021 | MOHAMMAD ESMAILI |
Contact Information
| Contractor | L D L General Contractors Inc; Lic. No.: 856503-B | 7216 LITTLER COURT MOORPARK, CA 93021 |
| Engineer | Vlachos,, Manuel Vassilios; Lic. No.: C64976 | 6832 RIDGEMARK DR MOORPARK, CA 93021 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 6/8/2021 | Not Ready for Inspection | MATT KELLERMAN |
| Excavation/Setback/Form/Re-Bar | 6/8/2021 | Partial Approval | MATT KELLERMAN |
| HVAC-Rough | 6/8/2021 | No Access for Inspection | MATT KELLERMAN |
| PLUMBING-Rough | 6/8/2021 | Not Ready for Inspection | MATT KELLERMAN |
| ELECTRICAL-Rough | 6/14/2021 | Partial Approval | MATT KELLERMAN |
| Excavation/Setback/Form/Re-Bar | 6/14/2021 | Partial Approval | MATT KELLERMAN |
| Footing/Foundation/Slab | 6/14/2021 | Partial Approval | MATT KELLERMAN |
| HVAC-Rough | 6/14/2021 | Partial Approval | MATT KELLERMAN |
| PLUMBING-Rough | 6/14/2021 | Partial Approval | MATT KELLERMAN |
| BUILDING-Rough-Frame | 6/18/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 6/21/2021 | Partial Approval | MATT KELLERMAN |
| Wood Frame | 6/21/2021 | Partial Approval | MATT KELLERMAN |
| Excavation/Setback/Form/Re-Bar | 6/23/2021 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Drilled-In Anchors | 6/24/2021 | Conditional Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 6/24/2021 | Conditional Approval | CHRISTOPHER WILSON |
| Drywall Nailing | 6/24/2021 | Partial Approval | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 7/1/2021 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 7/1/2021 | Partial Approval | CHRISTOPHER WILSON |
| HVAC-Rough | 7/1/2021 | Partial Approval | CHRISTOPHER WILSON |
| PLUMBING-Rough | 7/1/2021 | Partial Approval | CHRISTOPHER WILSON |
| Insulation | 7/2/2021 | Partial Approval | CHRISTOPHER WILSON |
| PLUMBING-Rough | 7/2/2021 | Partial Approval | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 7/27/2021 | Partial Approval | CHRISTOPHER WILSON |
| Insulation | 7/27/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Drywall Nailing | 7/30/2021 | Approved | KIM BEAUCHAMP |
| Interior/Exterior Lathing | 7/30/2021 | Approved | KIM BEAUCHAMP |
| ELECTRICAL-Rough | 8/3/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| HVAC-Rough | 8/3/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| PLUMBING-Rough | 8/3/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 8/9/2021 | Corrections Issued | CHRISTOPHER WILSON |
| HVAC-Rough | 8/9/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| PLUMBING-Rough | 8/9/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 8/10/2021 | Partial Approval | CHRISTOPHER WILSON |
| HVAC-Rough | 8/10/2021 | Partial Approval | CHRISTOPHER WILSON |
| PLUMBING-Rough | 8/10/2021 | Partial Approval | CHRISTOPHER WILSON |
| Drywall Nailing | 8/12/2021 | Partial Approval | CHRISTOPHER WILSON |
| Insulation | 8/12/2021 | Partial Approval | CHRISTOPHER WILSON |
| Drywall Nailing | 8/23/2021 | Partial Approval | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 8/23/2021 | Partial Approval | CHRISTOPHER WILSON |
| Drywall Nailing | 8/27/2021 | Partial Approval | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 8/27/2021 | Partial Approval | CHRISTOPHER WILSON |
| Gas Test | 3/22/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 4/7/2022 | Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 4/7/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Final | 4/7/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 4/7/2022 | Approved | CHRISTOPHER WILSON |
| Green Building Final | 4/7/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Green Building Rough | 4/7/2022 | Approved | CHRISTOPHER WILSON |
| HVAC-Final | 4/7/2022 | Corrections Issued | CHRISTOPHER WILSON |
| PLUMBING-Final | 4/7/2022 | Corrections Issued | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 4/7/2022 | SGSOV Approved | CHRISTOPHER WILSON |
| Service/Power Release | 4/7/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Smoke Detectors | 4/7/2022 | Approved | CHRISTOPHER WILSON |
| Final | 6/29/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Green Building Final | 6/29/2022 | Approved | CHRISTOPHER WILSON |
| Final | 9/7/2022 | OK to Issue CofO | CHRISTOPHER WILSON |