11073 W CALIFA ST 91601

Certificate Information: 11073 W CALIFA ST 91601

Application / Permit
21014-20000-00187
Plan Check / Job No.
B21VN00522
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 12'-4" x 16'-11" ATTACHED PATIO COVER AND 32'-10" x 12'-6" ADDITION TO (E) 18'-3" x 19'-2" DETACHED GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 7/9/2021
Issuing Office
Current Status
CofO Issued on 7/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/14/2021 APPLICANT
Assigned to Plan Check Engineer 2/4/2021 SARKIS HARABEDIAN
Corrections Issued 2/6/2021 SARKIS HARABEDIAN
Quality Review Completed 2/11/2021 STEVEN KIM
Plan Check Approved 7/9/2021 SARKIS HARABEDIAN
Issued 7/9/2021 APPLICANT
Building Plans Picked Up 7/13/2021 APPLICANT
CofO in Progress 5/16/2022 ARAM AVEDISIAN
CofO Issued 7/16/2022 MICHAEL SMITH
Permit Finaled 7/16/2022 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 2/12/2021 WALTER RAMIREZ
Construction within easement Cleared 2/12/2021 WALTER RAMIREZ
Address approval Cleared 2/16/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 2/16/2021 GABRIEL ROBLES
Sewer availability Cleared 2/16/2021 GABRIEL ROBLES
Hydrant and Access approval Cleared 4/21/2021 JOHN CONNEALLY
Low Impact Development Cleared 6/28/2021 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 6/28/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,
Engineer Arakelyan,, Aram; Lic. No.: C82796 145 S GLENOAKS BI 328      BURBANK, CA 91502

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/21/2021 Approved DANIEL DREW
Footing/Foundation/Slab 10/12/2021 Approved DANIEL DREW
BUILDING-Rough-Frame 12/6/2021 Partial Approval THOMAS FINNILA
Green Building Rough 12/6/2021 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 12/13/2021 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 12/13/2021 Approved ARAM AVEDISIAN
Green Building Rough 12/13/2021 Conditional Approval ARAM AVEDISIAN
HVAC-Rough 12/13/2021 Approved ARAM AVEDISIAN
PLUMBING-Rough 12/13/2021 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 12/20/2021 Partial Approval RYAN SALAZAR
Insulation 12/23/2021 Approved JACK KARGODORIAN
Sewer 1/10/2022 Corrections Issued MISAEL ESPARZA
Drywall Nailing 1/14/2022 Approved CALEB MEISTER
Green Building Rough 1/14/2022 Approved CALEB MEISTER
Sewer 1/14/2022 Approved CALEB MEISTER
Underground Mechanical 1/14/2022 Partial Approval CALEB MEISTER
Final 4/27/2022 Corrections Issued ARAM AVEDISIAN
Green Building Final 4/27/2022 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 4/27/2022 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 4/27/2022 Approved ARAM AVEDISIAN
Final 5/3/2022 Corrections Issued MICHAEL TEMPLE
Final 5/16/2022 OK to Issue CofO ARAM AVEDISIAN