16160 W MEADOWCREST ROAD 91403
Certificate Information: 16160 W MEADOWCREST ROAD 91403
- Application / Permit
- 21014-20000-00175
- Plan Check / Job No.
- B21VN00456
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 8'-9" X 13'-3" ADDITION TO ENLARGE (E) BEDROOM AND HALLWAY AND 6'-6" X 12'-9" IRREGULAR SHAPED ADDITION FOR (N) CLOSET TO (E) BEDROOM. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 4/20/2021
- Issuing Office
- Valley
- Current Status
- Issued on 4/20/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Building Plans Picked Up | 3/19/2020 | APPLICANT |
| Submitted | 1/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2021 | RAPHAEL ROSAS |
| Corrections Issued | 1/30/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 4/6/2021 | RAPHAEL ROSAS |
| Issued | 4/20/2021 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/5/2021 | MARKOS PEREZ-BRAN |
| Grading Pre-Inspection | Cleared | 3/10/2021 | BRIAN MILLER |
| Specific Plan | Cleared | 3/24/2021 | OLGA AYALA |
| ZI | Cleared | 3/24/2021 | OLGA AYALA |
| Roof/Waste drainage to street | Cleared | 4/8/2021 | MARKOS PEREZ-BRAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chamberlain,, Robert Douglas; Lic. No.: C67937 | 7235 DE CELIS PL VAN NUYS, CA 91406 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/4/2021 | Corrections Issued | JEFFREY PARD |
| Footing/Foundation/Slab | 5/4/2021 | Corrections Issued | JEFFREY PARD |
| Pre-Inspection | 5/25/2021 | Approved | RONALD COWAN |
| Drywall Nailing | 6/3/2021 | Partial Approval | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 6/3/2021 | Partial Approval | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 6/29/2021 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 6/29/2021 | Approved | VINCENT HANLEY |
| Final | 6/29/2021 | Partial Approval | VINCENT HANLEY |
| Footing/Foundation/Slab | 6/29/2021 | Approved | VINCENT HANLEY |
| Green Building Final | 6/29/2021 | Approved | VINCENT HANLEY |
| Green Building Rough | 6/29/2021 | Approved | VINCENT HANLEY |
| HVAC-Final | 6/29/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 6/29/2021 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 6/29/2021 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 6/29/2021 | Approved | VINCENT HANLEY |