19441 W PINE VALLEY AVE 91326
Certificate Information: 19441 W PINE VALLEY AVE 91326
- Application / Permit
- 21014-20000-00174
- Plan Check / Job No.
- B21VN00446
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO SINGLE FAMILY DWELLING ( 14' X 16'-5") AND INTERIOR REMODEL PER ENGINEER
- Permit Issued
- Issued on 4/13/2021
- Issuing Office
- Current Status
- CofO Issued on 11/4/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2021 | SELLA BENYAMIN |
| Corrections Issued | 2/2/2021 | SELLA BENYAMIN |
| Building Plans Picked Up | 2/3/2021 | APPLICANT |
| Plan Check Approved | 3/16/2021 | SELLA BENYAMIN |
| Issued | 4/13/2021 | APPLICANT |
| CofO in Progress | 11/4/2021 | DAVID SCANTLIN |
| Permit Finaled | 11/4/2021 | JOHN JANSON |
| CofO Issued | 11/4/2021 | JOHN JANSON |
| Permit Finaled | 11/4/2021 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 2/24/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Avila,, Albert Guerrero; Lic. No.: C41726 | 10034 GLADE AVNENUE CHATSWORTH, CA 91311 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 4/22/2021 | Partial Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 4/22/2021 | Approved | MICHAEL PELHAM |
| Footing/Foundation/Slab | 4/22/2021 | Approved | MICHAEL PELHAM |
| METHANE-Barrier | 4/22/2021 | Approved | MICHAEL PELHAM |
| METHANE-Subgrade | 4/22/2021 | Approved | MICHAEL PELHAM |
| PLUMBING-Rough | 4/22/2021 | Partial Approval | MICHAEL PELHAM |
| Pre-Inspection | 4/22/2021 | Partial Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 6/23/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Rough | 6/23/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| METHANE-Rough | 6/23/2021 | Approved | DAVID SCANTLIN |
| Rough-Elec/Plmb/HVAC | 6/23/2021 | Approved | DAVID SCANTLIN |
| Wood Frame | 6/23/2021 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 7/6/2021 | Corrections Issued | DAVID SANDOVAL |
| Green Building Rough | 7/6/2021 | Approved | DAVID SANDOVAL |
| Insulation | 7/6/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Interior/Exterior Lathing | 7/6/2021 | Partial Approval | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 7/9/2021 | Approved | MICHAEL PELHAM |
| Final | 10/13/2021 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 10/13/2021 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 10/13/2021 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 10/13/2021 | Approved | DAVID SCANTLIN |
| Final | 10/19/2021 | OK to Issue CofO | DAVID SCANTLIN |