5631 N WILLIS AVE 91411
Certificate Information: 5631 N WILLIS AVE 91411
- Application / Permit
- 21014-20000-00172
- Plan Check / Job No.
- B21VN00441
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF A 14'-10" x 33'-6" ADDITION TO CONSIST OF A BEDROOM AND A FULL BATHROOM. DESIGN PER WFPP.
- Permit Issued
- Issued on 1/19/2022
- Issuing Office
- Current Status
- CofO Issued on 9/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/26/2021 | LUIS RINCON |
| Corrections Issued | 1/27/2021 | LUIS RINCON |
| Applicant returned to address corrections | 6/1/2021 | LUIS RINCON |
| Applicant returned to address corrections | 6/30/2021 | LUIS RINCON |
| Applicant returned to address corrections | 10/29/2021 | LUIS RINCON |
| Plan Check Approved | 1/14/2022 | ANGELICA MARTINEZ |
| Issued | 1/19/2022 | APPLICANT |
| Building Plans Picked Up | 1/24/2022 | APPLICANT |
| CofO in Progress | 9/15/2022 | ALAN MORELOS |
| CofO Issued | 9/15/2022 | MICHAEL SMITH |
| Permit Finaled | 9/15/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/13/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 1/13/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/24/2022 | Approved | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Rough | 2/1/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Pre-Inspection | 2/1/2022 | Approved | RICHARD DOCKUS |
| Wood Frame | 2/1/2022 | Corrections Issued | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 2/4/2022 | Partial Approval | RICHARD DOCKUS |
| Excavation/Setback/Form/Re-Bar | 2/4/2022 | Approved | RICHARD DOCKUS |
| Green Building Rough | 2/4/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2022 | Partial Approval | KRISTEN CAUSEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| ELECTRICAL-Rough | 2/24/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2022 | Partial Approval | RICHARD DOCKUS |
| HVAC-Rough | 2/24/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Rough | 2/24/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| ELECTRICAL-Rough | 3/1/2022 | Approved | RICHARD DOCKUS |
| HVAC-Rough | 3/1/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 3/1/2022 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 3/8/2022 | Not Ready for Inspection | ALAN MORELOS |
| Green Building Rough | 3/8/2022 | Not Ready for Inspection | ALAN MORELOS |
| Insulation | 3/8/2022 | Not Ready for Inspection | ALAN MORELOS |
| Insulation | 3/11/2022 | No Access for Inspection | ALAN MORELOS |
| Insulation | 3/16/2022 | Not Ready for Inspection | ALAN MORELOS |
| Special/Order Compliance | 3/17/2022 | No Access for Inspection | MICHAEL TEMPLE |
| Insulation | 3/22/2022 | Corrections Issued | MICHAEL TEMPLE |
| Interior/Exterior Lathing | 3/29/2022 | Not Ready for Inspection | DAVID MATSON |
| BUILDING-Rough-Frame | 4/7/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Green Building Rough | 4/7/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Insulation | 4/7/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Interior/Exterior Lathing | 4/7/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 4/14/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Green Building Rough | 4/14/2022 | Approved | RICHARD DOCKUS |
| Insulation | 4/14/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Interior/Exterior Lathing | 4/14/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 4/26/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 4/26/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/26/2022 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 5/2/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 5/6/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 5/10/2022 | Approved | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2022 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 5/13/2022 | Corrections Issued | DEANDRE HOFFMAN |
| Insulation | 5/17/2022 | Corrections Issued | RICHARD DOCKUS |
| Insulation | 5/23/2022 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 5/23/2022 | Partial Approval | ALAN MORELOS |
| Drywall Nailing | 5/31/2022 | Partial Approval | DEANDRE HOFFMAN |
| Drywall Nailing | 9/1/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 9/12/2022 | Corrections Issued | ROBERT GOLD |
| Final | 9/12/2022 | Not Ready for Inspection | ROBERT GOLD |
| Green Building Final | 9/12/2022 | Approved | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 9/12/2022 | SGSOV Approved | ROBERT GOLD |
| ELECTRICAL-Final | 9/14/2022 | Approved | ALAN MORELOS |
| Final | 9/14/2022 | OK to Issue CofO | ALAN MORELOS |
| Final | 9/14/2022 | Off-Hour Fees Due | |
| HVAC-Final | 9/14/2022 | Approved | ALAN MORELOS |
| PLUMBING-Final | 9/14/2022 | Approved | ALAN MORELOS |
| Smoke Detectors | 9/14/2022 | Approved | ALAN MORELOS |
| Smoke Detectors | 9/14/2022 | Off-Hour Fees Due |