1122 S ALFRED ST 90035

Certificate Information: 1122 S ALFRED ST 90035

Application / Permit
21014-20000-00159
Plan Check / Job No.
B21VN00409
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO SFD FOR CLOSET AT BEDROOM. REMODEL BATHROOM
Permit Issued
Issued on 5/23/2021
Issuing Office
Current Status
CofO Issued on 2/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/12/2021 APPLICANT
Assigned to Plan Check Engineer 1/22/2021 JESSE ARELLANO
Corrections Issued 1/23/2021 JESSE ARELLANO
Applicant returned to address corrections 4/6/2021 JESSE ARELLANO
Plan Check Approved 5/6/2021 JESSE ARELLANO
Building Plans Picked Up 5/11/2021 APPLICANT
Issued 5/23/2021 APPLICANT
CofO in Progress 1/28/2022 JOSE AVILA
Permit Finaled 2/14/2022 DEROLD HAUFF
CofO Issued 2/14/2022 DEROLD HAUFF
Permit Finaled 2/14/2022 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/19/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 3/22/2021 CELINA MORENO
HPOZ Cleared 4/29/2021 JONATHAN KAPLAN
Green Code Cleared 5/5/2021 JESSE ARELLANO

Contact Information

Contractor Owner-Builder       ,
Engineer Adams,, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/18/2021 No Access for Inspection CALEB MEISTER
METHANE-Barrier 8/18/2021 No Access for Inspection CALEB MEISTER
METHANE-Subgrade 8/18/2021 No Access for Inspection CALEB MEISTER
Footing/Foundation/Slab 8/20/2021 Approved CALEB MEISTER
METHANE-Barrier 8/20/2021 Approved CALEB MEISTER
METHANE-Subgrade 8/20/2021 Approved CALEB MEISTER
PLUMBING-Rough 8/26/2021 Partial Approval KATHRYN BUTTERWORTH
Underground Mechanical 8/31/2021 Approved CALEB MEISTER
BUILDING-Rough-Frame 9/20/2021 Corrections Issued JOAQUIN GREENOUGH
Green Building Rough 9/20/2021 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Rough 9/20/2021 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 9/22/2021 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 9/22/2021 Corrections Issued SCOTT FINNILA
HVAC-Rough 9/22/2021 Approved SCOTT FINNILA
Insulation 9/28/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 9/28/2021 Partial Approval STUART CHAPMAN
Shower Pan 9/28/2021 Approved STUART CHAPMAN
Drywall Nailing 10/1/2021 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 10/1/2021 Approved ASHLEY THOMPSON
BUILDING-Rough-Frame 11/16/2021 Approved JOSE AVILA
Final 11/16/2021 Not Ready for Inspection JOSE AVILA
Green Building Final 11/16/2021 Approved JOSE AVILA
Green Building Rough 11/16/2021 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 11/16/2021 SGSOV Approved JOSE AVILA
Smoke Detectors 11/16/2021 Corrections Issued JOSE AVILA
Final 12/8/2021 Corrections Issued JOSE AVILA
Smoke Detectors 12/8/2021 Approved JOSE AVILA
Final 1/27/2022 OK to Issue CofO JOSE AVILA