6524 N FARRALONE AVE 91303

Certificate Information: 6524 N FARRALONE AVE 91303

Application / Permit
21014-20000-00151
Plan Check / Job No.
B21VN00377
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
10'-9" X 9'-9" ADDITION FOR NEW BATHROOM AND LAUNDRY ROOM
Permit Issued
Issued on 3/1/2021
Issuing Office
Current Status
CofO Issued on 12/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/14/2021 APPLICANT
Assigned to Plan Check Engineer 1/26/2021 JEROME MAGAT PALMA
Corrections Issued 1/26/2021 JEROME MAGAT PALMA
Plan Check Approved 3/1/2021 JEROME MAGAT PALMA
Issued 3/1/2021 APPLICANT
Building Plans Picked Up 3/2/2021 APPLICANT
CofO in Progress 12/14/2021 TROY SANDERS
CofO Issued 12/12/2022 JOHN JANSON
Permit Finaled 12/12/2022 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/28/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 1/28/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 1/28/2021 LEE GUILBEAUX
Public Works-Sewers Cleared 1/28/2021 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Maalouf,, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/8/2021 Partial Approval TROY SANDERS
Sewer 4/8/2021 Approved TROY SANDERS
Excavation/Setback/Form/Re-Bar 4/14/2021 Approved TROY SANDERS
Footing/Foundation/Slab 4/14/2021 Approved TROY SANDERS
ELECTRICAL-Rough 5/6/2021 Not Ready for Inspection TROY SANDERS
PLUMBING-Rough 5/6/2021 Not Ready for Inspection TROY SANDERS
ELECTRICAL-Rough 5/17/2021 Approved TROY SANDERS
PLUMBING-Rough 5/17/2021 Approved TROY SANDERS
BUILDING-Rough-Frame 5/20/2021 Approved TROY SANDERS
HVAC-Rough 5/20/2021 Approved TROY SANDERS
Insulation 5/20/2021 Approved TROY SANDERS
BUILDING-Rough-Frame 6/2/2021 Approved TROY SANDERS
Drywall Nailing 6/2/2021 Approved TROY SANDERS
Green Building Rough 6/2/2021 Approved TROY SANDERS
Interior/Exterior Lathing 6/2/2021 Partial Approval TROY SANDERS
Final 7/13/2021 Corrections Issued TROY SANDERS
Green Building Final 7/13/2021 Corrections Issued TROY SANDERS
SGSOV-Seismic Gas S/O Valve 7/13/2021 SGSOV Approved TROY SANDERS
Smoke Detectors 7/13/2021 Approved TROY SANDERS
Final 11/5/2021 Not Ready for Inspection TROY SANDERS
Green Building Final 11/5/2021 Not Ready for Inspection TROY SANDERS
Final 12/14/2021 OK to Issue CofO TROY SANDERS
Green Building Final 12/14/2021 Approved TROY SANDERS