4975 N CHIMINEAS AVE 91356
Certificate Information: 4975 N CHIMINEAS AVE 91356
- Application / Permit
- 21014-20000-00149
- Plan Check / Job No.
- B21VN00368
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION (23'-1" X 12'-4") TO ENLARGE FAMILY ROOM. WORK PER ENGINEER
- Permit Issued
- Issued on 6/8/2021
- Issuing Office
- Valley
- Current Status
- Issued on 6/8/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/29/2021 | ROSENDO MEDINA |
| Corrections Issued | 2/1/2021 | ROSENDO MEDINA |
| Plan Check Approved | 2/24/2021 | ROSENDO MEDINA |
| Building Plans Picked Up | 2/25/2021 | APPLICANT |
| Issued | 6/8/2021 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/5/2021 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 2/5/2021 | JOHN TRIANTAFYLLOS |
| Grading Pre-Inspection | Cleared | 2/24/2021 | ROSENDO MEDINA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Aronianpour,, Eilan; Lic. No.: C88101 | 7242 JELLICO AVE LAKE BALBOA, CA 91406 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/10/2021 | Approved | DAVID SANDOVAL |
| Footing/Foundation/Slab | 9/10/2021 | Corrections Issued | DAVID SANDOVAL |
| Deputy Drilled-In Anchors | 9/17/2021 | No Access for Inspection | DAVID SANDOVAL |
| Wood Frame | 9/20/2021 | Approved | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2021 | Partial Approval | DAVID SANDOVAL |
| ELECTRICAL-Rough | 9/27/2021 | Approved | DAVID SANDOVAL |
| Deputy Wood Construction | 9/29/2021 | Conditional Approval | DAVID SANDOVAL |
| Insulation | 9/29/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 10/18/2021 | Approved | DAVID SANDOVAL |
| Green Building Rough | 10/18/2021 | Approved | DAVID SANDOVAL |
| Insulation | 10/18/2021 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 10/18/2021 | Partial Approval | DAVID SANDOVAL |
| Drywall Nailing | 11/19/2021 | Approved | MORRIS JACKSON |
| Final | 2/23/2022 | Corrections Issued | DAVID SANDOVAL |
| Footing/Foundation/Slab | 2/23/2022 | Approved | DAVID SANDOVAL |
| Green Building Final | 2/23/2022 | Approved | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 2/23/2022 | SGSOV Approved | DAVID SANDOVAL |
| Smoke Detectors | 2/23/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Final | 3/1/2022 | Partial Approval | DAVID SANDOVAL |
| Smoke Detectors | 3/1/2022 | Approved | DAVID SANDOVAL |