8035 N WYNNE AVE 91335

Certificate Information: 8035 N WYNNE AVE 91335

Application / Permit
21014-20000-00131
Plan Check / Job No.
B21VN00323
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX DETACHED GARAGE INTO ACCESSORY DWELLING UNIT W/ 22'4"X 14'8" ADDITION PER ORD #186,481.
Permit Issued
Issued on 5/18/2021
Issuing Office
Current Status
CofO Issued on 11/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/11/2021 APPLICANT
Assigned to Plan Check Engineer 1/22/2021 HAYATO TSUCHIYA
Corrections Issued 1/24/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 2/24/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 3/7/2021 HAYATO TSUCHIYA
Plan Check Approved 4/17/2021 HAYATO TSUCHIYA
Building Plans Picked Up 4/26/2021 APPLICANT
Issued 5/18/2021 APPLICANT
CofO in Progress 11/11/2021 VINCENT HANLEY
Permit Finaled 11/15/2021 MICHAEL SMITH
CofO Issued 11/15/2021 MICHAEL SMITH
Permit Finaled 11/15/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/26/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 1/26/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 1/27/2021 GABRIEL ROBLES
Sewer availability Cleared 1/27/2021 GABRIEL ROBLES
Construction near power lines Cleared 4/12/2021 WALTER RAMIREZ

Contact Information

Contractor Doobek Builders; Lic. No.: 980653-B 5308 DERRY AVE   I-101, 102    AGOURA HILLS, CA 91301
Engineer Tabirara,, Vernon Nicolas; Lic. No.: C75492 17520 DAPHNE AVE      TORRANCE, CA 90504

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/2/2021 Approved DAVID SCANTLIN
PLUMBING-Rough 6/2/2021 Partial Approval DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 6/22/2021 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 7/14/2021 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 7/14/2021 Approved VINCENT HANLEY
Green Building Rough 7/14/2021 Not Ready for Inspection VINCENT HANLEY
Rough-Elec/Plmb/HVAC 7/14/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 7/30/2021 Partial Approval VINCENT HANLEY
Green Building Rough 7/30/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 7/30/2021 Partial Approval VINCENT HANLEY
Shower Pan 7/30/2021 Approved VINCENT HANLEY
Insulation 8/4/2021 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 8/9/2021 Approved RYAN SALAZAR
Drywall Nailing 8/10/2021 Not Ready for Inspection RYAN SALAZAR
BUILDING-Rough-Frame 8/17/2021 Approved RYAN SALAZAR
Drywall Nailing 8/17/2021 Approved RYAN SALAZAR
Interior/Exterior Lathing 8/17/2021 Approved RYAN SALAZAR
ELECTRICAL-Final 10/29/2021 Approved VINCENT HANLEY
Final 10/29/2021 Corrections Issued VINCENT HANLEY
Gas Test 10/29/2021 Approved VINCENT HANLEY
Green Building Final 10/29/2021 Approved VINCENT HANLEY
HVAC-Final 10/29/2021 Corrections Issued VINCENT HANLEY
PLUMBING-Final 10/29/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 10/29/2021 SGSOV Approved VINCENT HANLEY
Service/Power Release 10/29/2021 Approved VINCENT HANLEY
Smoke Detectors 10/29/2021 Approved VINCENT HANLEY
Final 11/10/2021 OK to Issue CofO VINCENT HANLEY
HVAC-Final 11/10/2021 Approved VINCENT HANLEY