837 S GENESEE AVE 90036

Certificate Information: 837 S GENESEE AVE 90036

Application / Permit
21014-20000-00104
Plan Check / Job No.
B21VN00267
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 34'-1" x 36'-8" IRR. SHAPED ADDITION TO (E) SINGLE FAMILY DWELLING AND INTERIOR REMODEL; AUTOMATIC SPRINKLER SYSTEM IS REQUIRED
Permit Issued
Issued on 9/21/2023
Issuing Office
Valley
Current Status
Issued on 9/21/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/8/2021 APPLICANT
Assigned to Plan Check Engineer 1/28/2021 SEAN SHAHMIRI
Corrections Issued 1/29/2021 SEAN SHAHMIRI
Quality Review Completed 2/18/2021 OMID HEDAYAT
Building Plans Picked Up 2/18/2021 APPLICANT
Applicant returned to address corrections 7/16/2022 SEAN SHAHMIRI
Plan Check Approved 8/16/2022 SEAN SHAHMIRI
Issued 9/21/2023 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 2/24/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 3/15/2021 WALLIE JONG
Low Impact Development Cleared 11/3/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 11/4/2021 WALLIE JONG
HPOZ Cleared 8/2/2022 CHRISTINA PARK

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Shiver Construction Inc; Lic. No.: 649585-B 5354 CAPTAINS PLACE      AGOURA HILLS, CA 91301

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/27/2023 Conditional Approval CHARLES BOGHOSKHAN
Excavation/Setback/Form/Re-Bar 11/1/2023 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 12/5/2023 Partial Approval RICHARD DOCKUS
PLUMBING-Rough 12/5/2023 Partial Approval RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 4/8/2024 Partial Approval RONNIE MINDANAO
Green Building Rough 4/8/2024 Not Ready for Inspection RONNIE MINDANAO
METHANE-Rough 4/8/2024 Approved RONNIE MINDANAO
BUILDING-Rough-Frame 6/3/2024 Not Ready for Inspection RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 6/3/2024 Partial Approval RONNIE MINDANAO
Green Building Rough 6/3/2024 Not Ready for Inspection RONNIE MINDANAO
Gas Test 6/13/2024 Approved RICHARD DOCKUS
Interior/Exterior Lathing 6/13/2024 Corrections Issued RICHARD DOCKUS
PLUMBING-Rough 6/13/2024 Approved RICHARD DOCKUS
ELECTRICAL-Rough 6/14/2024 Approved RICHARD DOCKUS
HVAC-Rough 6/14/2024 Corrections Issued RICHARD DOCKUS
HVAC-Rough 6/21/2024 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 6/25/2024 Corrections Issued RONNIE MINDANAO
Green Building Rough 6/25/2024 Not Ready for Inspection RONNIE MINDANAO
BUILDING-Rough-Frame 7/3/2024 Conditional Approval RONNIE MINDANAO
Green Building Rough 7/3/2024 Approved RONNIE MINDANAO
Insulation 7/3/2024 Approved RONNIE MINDANAO
Interior/Exterior Lathing 7/3/2024 Conditional Approval RONNIE MINDANAO
Shower Pan 7/9/2024 Approved RONNIE MINDANAO
Drywall Nailing 7/15/2024 Approved BRENDAN MORELLI
Interior/Exterior Lathing 7/17/2024 Partial Approval RONNIE MINDANAO
Interior/Exterior Lathing 7/30/2024 Approved RONNIE MINDANAO
ELECTRICAL-Final 1/24/2025 Corrections Issued RONNIE MINDANAO
HVAC-Final 1/24/2025 Approved RONNIE MINDANAO
PLUMBING-Final 1/24/2025 Corrections Issued RONNIE MINDANAO
BUILDING-Rough-Frame 2/24/2025 Approved RONNIE MINDANAO
Final 2/24/2025 Corrections Issued RONNIE MINDANAO
Footing/Foundation/Slab 2/24/2025 Approved RONNIE MINDANAO
Green Building Final 2/24/2025 Approved RONNIE MINDANAO
METHANE-Barrier 2/24/2025 Approved RONNIE MINDANAO
METHANE-Subgrade 2/24/2025 Approved RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 2/24/2025 SGSOV Approved RONNIE MINDANAO
Smoke Detectors 2/24/2025 Not Ready for Inspection RONNIE MINDANAO
Final 2/26/2025 Corrections Issued RONNIE MINDANAO
Gas Test 2/26/2025 Approved RONNIE MINDANAO
Smoke Detectors 2/26/2025 Approved RONNIE MINDANAO