436 S ROSSMORE AVE 90020
Certificate Information: 436 S ROSSMORE AVE 90020
- Application / Permit
- 21014-20000-00088
- Plan Check / Job No.
- B21VN00185
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT PORTION OF 1ST FLOOR AND ADD ACCESSORY DWELLING UNIT TO EXISTING 2-STORY GARAGE AND ACCESSORY STRUCTURE. 1/2 BATH WITH EXTERIOR ACCESS FOR POOL. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT
- Permit Issued
- Issued on 9/20/2021
- Issuing Office
- Current Status
- CofO Issued on 12/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2021 | ALYSSA N NARCISO |
| Corrections Issued | 2/5/2021 | ALYSSA N NARCISO |
| Quality Review Completed | 2/10/2021 | STEVEN KIM |
| Building Plans Picked Up | 2/10/2021 | APPLICANT |
| Applicant returned to address corrections | 7/7/2021 | ALYSSA N NARCISO |
| Plan Check Approved | 8/30/2021 | MOHAMMAD ESMAILI |
| Issued | 9/20/2021 | APPLICANT |
| CofO in Progress | 10/5/2022 | MICHAEL LEWIS |
| Permit Finaled | 12/7/2022 | DEROLD HAUFF |
| CofO Issued | 12/7/2022 | DEROLD HAUFF |
| Permit Finaled | 12/7/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/11/2021 | JUAN ASHTON |
| Eng Process Fee Ord 176,300 | Cleared | 3/11/2021 | JUAN ASHTON |
| Sewer availability | Cleared | 3/12/2021 | JUAN ASHTON |
| HPOZ | Cleared | 5/5/2021 | SUKI GERSHENHORN |
| Historic monument | Cleared | 5/5/2021 | SUKI GERSHENHORN |
| Miscellaneous | Cleared | 5/5/2021 | SUKI GERSHENHORN |
| Hydrant and Access approval | Cleared | 5/11/2021 | JOHN CONNEALLY |
| Construction near power lines | Cleared | 5/20/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 5/20/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 6/10/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 6/18/2021 | THAN WIN |
Contact Information
| Architect | Scrafano,, Elissa F; Lic. No.: C26071 | 163 N SYCAMORE LOS ANGELES, CA 90036 |
| Contractor | Hacienda Lopez Construction Inc; Lic. No.: 910123-B | 2140 NADULA DRIVE HACIENDA HEIGHTS, CA 91745 |
| Engineer | Manalo,, Philip Casis; Lic. No.: S3823 | 9547 WYSTONE AVE NORTHRIDGE, CA 91324 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/29/2021 | Approved | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 10/4/2021 | Partial Approval | ARTHUR SARGSYAN |
| METHANE-Barrier | 10/4/2021 | Partial Approval | ARTHUR SARGSYAN |
| METHANE-Subgrade | 10/4/2021 | Partial Approval | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 10/22/2021 | Partial Approval | JOSEPH MCGARRY |
| METHANE-Rough | 10/22/2021 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 10/22/2021 | Approved | JOSEPH MCGARRY |
| Deputy Wood Construction | 10/26/2021 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 11/22/2021 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 11/22/2021 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 11/29/2021 | Approved | ARTHUR SARGSYAN |
| Green Building Rough | 11/29/2021 | Approved | ARTHUR SARGSYAN |
| Insulation | 1/4/2022 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 1/28/2022 | Approved | ARTHUR SARGSYAN |
| Shower Pan | 1/28/2022 | Approved | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 2/4/2022 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Final | 7/8/2022 | Corrections Issued | ADAM ESCOTO |
| Final | 7/8/2022 | Corrections Issued | ADAM ESCOTO |
| Footing/Foundation/Slab | 7/8/2022 | Approved | ADAM ESCOTO |
| Green Building Final | 7/8/2022 | Not Ready for Inspection | ADAM ESCOTO |
| HVAC-Final | 7/8/2022 | Corrections Issued | ADAM ESCOTO |
| METHANE-Barrier | 7/8/2022 | Approved | ADAM ESCOTO |
| METHANE-Subgrade | 7/8/2022 | Approved | ADAM ESCOTO |
| PLUMBING-Final | 7/8/2022 | Corrections Issued | ADAM ESCOTO |
| SGSOV-Seismic Gas S/O Valve | 7/8/2022 | SGSOV Not Ready | ADAM ESCOTO |
| Smoke Detectors | 7/8/2022 | Corrections Issued | ADAM ESCOTO |
| ELECTRICAL-Final | 9/20/2022 | Partial Inspection | MICHAEL LEWIS |
| Final | 9/20/2022 | Partial Inspection | MICHAEL LEWIS |
| Green Building Final | 9/20/2022 | Approved | MICHAEL LEWIS |
| HVAC-Final | 9/20/2022 | Approved | MICHAEL LEWIS |
| PLUMBING-Final | 9/20/2022 | Partial Inspection | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 9/20/2022 | SGSOV Approved | MICHAEL LEWIS |
| Smoke Detectors | 9/20/2022 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 10/4/2022 | Approved | MICHAEL LEWIS |
| Final | 10/4/2022 | OK to Issue CofO | MICHAEL LEWIS |
| HVAC-Final | 10/4/2022 | Approved | MICHAEL LEWIS |
| PLUMBING-Final | 10/4/2022 | Approved | MICHAEL LEWIS |