16521 W JERSEY ST 91344
Certificate Information: 16521 W JERSEY ST 91344
- Application / Permit
- 21014-20000-00076
- Plan Check / Job No.
- B21VN00153
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- IRREGULAR SHAPE ADDITION OF 14'X 19'-3" BEDROOM / ENTRY HALL AND 5'-4"X 5' ENTRY PORCH IN FRONT OF (E) SFD W/ATT.GARAGE.
- Permit Issued
- Issued on 8/3/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/22/2021 | PARISA ZAHABI |
| Corrections Issued | 1/22/2021 | PARISA ZAHABI |
| Applicant returned to address corrections | 6/4/2021 | PARISA ZAHABI |
| Applicant returned to address corrections | 7/8/2022 | MOHAMMAD ESMAILI |
| Building Plans Picked Up | 7/11/2022 | APPLICANT |
| Plan Check Approved | 7/27/2022 | SERGIO MUNIZ |
| Issued | 8/3/2022 | APPLICANT |
| CofO in Progress | 1/6/2023 | CHRISTOPHER DELLEFIELD |
| CofO in Progress | 1/10/2023 | JAVIER RAMOS JR |
| CofO Issued | 1/21/2023 | MICHAEL SMITH |
| Permit Finaled | 1/21/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/8/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/13/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 7/13/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 7/13/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 7/13/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 7/13/2022 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Baluyut,, Agustin Pangilinan; Lic. No.: C66025 | 22828 S CYPRESS DR CARSON, CA 90745 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/4/2022 | Conditional Approval | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 8/12/2022 | Corrections Issued | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 8/16/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 9/20/2022 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2022 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 9/20/2022 | Approved | JAVIER RAMOS JR |
| Wood Frame | 9/20/2022 | Corrections Issued | JAVIER RAMOS JR |
| Deputy Wood Construction | 9/23/2022 | Conditional Approval | JAVIER RAMOS JR |
| Insulation | 9/28/2022 | Approved | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 9/28/2022 | Approved | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 10/5/2022 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 10/5/2022 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 10/5/2022 | Approved | JAVIER RAMOS JR |
| Final | 11/17/2022 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 11/17/2022 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 11/17/2022 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 11/17/2022 | Approved | JAVIER RAMOS JR |