7230 N WISH AVE 91406

Certificate Information: 7230 N WISH AVE 91406

Application / Permit
21014-20000-00063
Plan Check / Job No.
B21VN00126
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL, 28'-10" X 40'-0" ADDITION TO (E) SFD PER ENGINEERING.
Permit Issued
Issued on 5/20/2022
Issuing Office
Valley
Current Status
Issued on 5/20/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/6/2021 APPLICANT
Assigned to Plan Check Engineer 1/15/2021 ARTIN ZARUKIAN
Corrections Issued 1/16/2021 ARTIN ZARUKIAN
Plan Check Approved 3/22/2022 ARTIN ZARUKIAN
Building Plans Picked Up 5/16/2022 APPLICANT
Issued 5/20/2022 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/5/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 3/5/2021 JOHN TRIANTAFYLLOS
Low Impact Development Cleared 3/1/2022 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 3/1/2022 JOHN LIN

Contact Information

Contractor Benson Construction; Lic. No.: 890260-B 7230 WISH AVE      VAN NUYS, CA 91406
Engineer Husain,, Shahzain; Lic. No.: C62744 1843 MONTGOMERY RD      THOUSAND OAKS, CA 91360

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/14/2022 Corrections Issued ALAN MORELOS
Sewer 6/14/2022 Approved ALAN MORELOS
Footing/Foundation/Slab 6/17/2022 Approved ALAN MORELOS
Floor/Roof Diaphrgm/Shear Wall 7/20/2022 Partial Approval ALAN MORELOS
PLUMBING-Rough 7/20/2022 Partial Approval ALAN MORELOS
Special/Order Compliance 7/20/2022 Corrections Issued ALAN MORELOS
Floor/Roof Diaphrgm/Shear Wall 8/12/2022 Approved RAUL OLAGI
Insulation 8/12/2022 Partial Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 10/17/2022 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 10/21/2022 Conditional Approval RAUL OLAGI
ELECTRICAL-Rough 5/10/2024 Approved RAUL OLAGI
PLUMBING-Rough 5/10/2024 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 6/28/2024 Corrections Issued RAUL OLAGI
Green Building Rough 6/28/2024 Not Ready for Inspection RAUL OLAGI
HVAC-Rough 6/28/2024 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 6/28/2024 Approved RAUL OLAGI
Interior/Exterior Lathing 7/3/2024 Partial Approval RAUL OLAGI
HVAC-Rough 7/11/2024 Approved RAUL OLAGI
Insulation 8/23/2024 Corrections Issued SALVADOR MARTINEZ
BUILDING-Rough-Frame 8/27/2024 Approved RAUL OLAGI
Green Building Rough 8/27/2024 Approved RAUL OLAGI
Insulation 8/27/2024 Partial Approval RAUL OLAGI
Drywall Nailing 8/29/2024 Approved RAUL OLAGI
Insulation 8/29/2024 Approved RAUL OLAGI
Shower Pan 9/27/2024 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 10/3/2024 Approved DAVID ANDERSON