5218 N LOLETA AVE 90041

Certificate Information: 5218 N LOLETA AVE 90041

Application / Permit
21014-20000-00036
Plan Check / Job No.
B21VN00085
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE ALL (E) INTERIOR AND EXTERIOR WALLS EXCEPT FOR 8'-3" LF IN FRONT OF THE DWELLING AND REBUILD IRR. SHAPED ONE-STORY 38'-0" x 75'-2" SINGLE FAMILY DWELLING WITH NEW ADDITION (SEE COMMENTS); AUTOMATIC SPRINKLER SYSTEM IS REQUIRED.
Permit Issued
Issued on 7/21/2021
Issuing Office
Current Status
CofO Issued on 6/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/5/2021 APPLICANT
Assigned to Plan Check Engineer 1/21/2021 SEAN SHAHMIRI
Corrections Issued 1/23/2021 SEAN SHAHMIRI
Quality Review Completed 2/8/2021 OMID HEDAYAT
Building Plans Picked Up 2/9/2021 APPLICANT
Applicant returned to address corrections 7/6/2021 SEAN SHAHMIRI
Applicant returned to address corrections 7/13/2021 SEAN SHAHMIRI
Applicant returned to address corrections 7/21/2021 SEAN SHAHMIRI
Plan Check Approved 7/21/2021 SEAN SHAHMIRI
Issued 7/21/2021 APPLICANT
CofO in Progress 5/4/2022 CRAIG VAUGHAN
Permit Finaled 6/3/2022 DEROLD HAUFF
CofO Issued 6/3/2022 DEROLD HAUFF
Permit Finaled 6/3/2022 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 2/17/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 2/18/2021 WALLIE JONG
Low Impact Development Cleared 3/29/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 3/31/2021 ROSA SILVA
Hydrant and Access approval Cleared 4/5/2021 KURT CORRAL
Grading Pre-Inspection Cleared 7/2/2021 SEAN SHAHMIRI

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/19/2021 Partial Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 9/7/2021 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 9/21/2021 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 9/21/2021 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 10/22/2021 Partial Approval DANIEL GONZALEZ
Green Building Rough 10/22/2021 Not Ready for Inspection DANIEL GONZALEZ
Underground Mechanical 10/22/2021 Not Ready for Inspection DANIEL GONZALEZ
Underground Mechanical 10/27/2021 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 11/24/2021 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 11/24/2021 Not Ready for Inspection CRAIG VAUGHAN
Green Building Rough 11/24/2021 Approved CRAIG VAUGHAN
HVAC-Rough 11/24/2021 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 11/24/2021 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 12/1/2021 Approved CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 12/1/2021 Approved CRAIG VAUGHAN
Verify Sprinkler Sign Off 12/1/2021 Approved CRAIG VAUGHAN
Wood Frame 12/1/2021 Approved CRAIG VAUGHAN
Insulation 12/17/2021 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 12/17/2021 Partial Approval CRAIG VAUGHAN
Drywall Nailing 12/30/2021 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 12/30/2021 Approved CRAIG VAUGHAN
Shower Pan 12/30/2021 Approved CRAIG VAUGHAN
Final 4/28/2022 Corrections Issued CRAIG VAUGHAN
Gas Test 4/28/2022 Approved CRAIG VAUGHAN
Green Building Final 4/28/2022 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 4/28/2022 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 4/28/2022 Approved CRAIG VAUGHAN
Final 5/3/2022 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 5/3/2022 Approved CRAIG VAUGHAN