22724 W CRESPI ST 91364

Certificate Information: 22724 W CRESPI ST 91364

Application / Permit
21014-20000-00034
Plan Check / Job No.
B21VN00083
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF 2ND STORY BEDROOM, BATHROOM & BALCONY TO (E) 1-STORY SFD W/ ATTACHED GARAGE. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 12/22/2021
Issuing Office
Current Status
CofO Issued on 5/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/5/2021 APPLICANT
Assigned to Plan Check Engineer 1/21/2021 NILOOFAR MEHRAIN
Corrections Issued 1/26/2021 NILOOFAR MEHRAIN
Quality Review Completed 1/26/2021 CHON CHIO KUO
Building Plans Picked Up 1/26/2021 APPLICANT
Applicant returned to address corrections 12/7/2021 COLIN LOREDO
Plan Check Approved 12/22/2021 COLIN LOREDO
Issued 12/22/2021 APPLICANT
CofO in Progress 5/15/2023 PETER FOLLING
Permit Finaled 5/17/2023 MICHAEL SMITH
CofO Issued 5/17/2023 MICHAEL SMITH
Permit Finaled 5/17/2023 MICHAEL SMITH

Permit Application Clearance Information

Low Impact Development Cleared 8/30/2021 YVAINNE GALSIM
BHO/Hillside ordinance Cleared 9/1/2021 GABRIEL ROBLES
BHO/Hillside ordinance Cleared 9/1/2021 GABRIEL ROBLES
BHO/Hillside ordinance Cleared 9/1/2021 GABRIEL ROBLES
BHO/Hillside ordinance Cleared 9/1/2021 GABRIEL ROBLES
BHO/Hillside ordinance Cleared 9/1/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 9/1/2021 GABRIEL ROBLES
Sewer availability Cleared 10/30/2021 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 11/2/2021 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 11/5/2021 KURT CORRAL
GPI Written Notices Cleared 12/7/2021 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 12/7/2021 NILOOFAR MEHRAIN

Contact Information

Contractor Owner-Builder       ,
Engineer Boules,, George Helmy; Lic. No.: C64144 29082 MADRID PL      CASTAIC, CA 91384

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/23/2022 No Access for Inspection PETER FOLLING
Pre-Inspection 3/25/2022 Approved PETER FOLLING
Pre-Inspection 6/14/2022 Not Ready for Inspection PETER FOLLING
Footing/Foundation/Slab 7/7/2022 Partial Approval PETER FOLLING
Deputy Drilled-In Anchors 7/8/2022 Conditional Approval MICHAEL SMITH
Deputy Drilled-In Anchors 7/15/2022 No Access for Inspection PETER FOLLING
Footing/Foundation/Slab 7/18/2022 Partial Approval PETER FOLLING
Deputy Drilled-In Anchors 7/25/2022 Approved DAVID SANDOVAL
Footing/Foundation/Slab 7/25/2022 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 10/24/2022 Corrections Issued PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 11/2/2022 Approved PETER FOLLING
BUILDING-Rough-Frame 11/16/2022 Approved PETER FOLLING
Green Building Rough 11/16/2022 Approved PETER FOLLING
MERV13>=Rough 11/16/2022 Approved PETER FOLLING
Rough-Elec/Plmb/HVAC 11/16/2022 Approved PETER FOLLING
Insulation 11/21/2022 Approved PETER FOLLING
Drywall Nailing 11/23/2022 Approved MORRIS JACKSON
Interior/Exterior Lathing 11/23/2022 Partial Approval MORRIS JACKSON
ELECTRICAL-Final 3/17/2023 Not Ready for Inspection PETER FOLLING
Final 3/17/2023 Corrections Issued PETER FOLLING
Green Building Final 3/17/2023 Approved PETER FOLLING
HVAC-Final 3/17/2023 Approved PETER FOLLING
MERV13>=Final 3/17/2023 Approved PETER FOLLING
PLUMBING-Final 3/17/2023 Approved PETER FOLLING
SGSOV-Seismic Gas S/O Valve 3/17/2023 SGSOV Approved PETER FOLLING
Smoke Detectors 3/17/2023 Approved PETER FOLLING
ELECTRICAL-Final 5/8/2023 Approved PETER FOLLING
Final 5/8/2023 Corrections Issued PETER FOLLING
HVAC-Final 5/8/2023 Approved PETER FOLLING
PLUMBING-Final 5/8/2023 Approved PETER FOLLING
Final 5/12/2023 OK to Issue CofO PETER FOLLING