12229 W TWEED LANE 90049
Certificate Information: 12229 W TWEED LANE 90049
- Application / Permit
- 21014-20000-00030
- Plan Check / Job No.
- B21VN00078
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1ST & 2ND STORY ADDITION, INTERIOR REMODEL, NEW ROOF DECK AND PLANTER AND REROOF TO (E) 2-STORY SINGLE FAMILY DWELLING. REPLACE ALL WINDOWS AND DOORS. NFPA 13 D FIRE SPRINKLERS REQUIRED
- Permit Issued
- Issued on 8/27/2021
- Issuing Office
- Current Status
- CofO Issued on 3/20/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2021 | ALYSSA N NARCISO |
| Corrections Issued | 2/5/2021 | ALYSSA N NARCISO |
| Quality Review Completed | 2/10/2021 | STEVEN KIM |
| Building Plans Picked Up | 2/10/2021 | APPLICANT |
| Applicant returned to address corrections | 6/29/2021 | ALYSSA N NARCISO |
| Plan Check Approved | 8/27/2021 | MOHAMMAD ESMAILI |
| Issued | 8/27/2021 | APPLICANT |
| CofO in Progress | 3/17/2023 | OGANES TARAKHCHYAN |
| Permit Finaled | 3/20/2023 | DANIEL ORRANTE |
| CofO Issued | 3/20/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/20/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Sewer availability | Cleared | 4/9/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/13/2021 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 6/1/2021 | KIRK LINKLATER |
| Miscellaneous | Cleared | 6/1/2021 | MIGUEL GAMBOA |
| Hydrant and Access approval | Cleared | 7/23/2021 | MATTHEW CRAIG |
| Roof/Waste drainage to street | Cleared | 7/26/2021 | DINAH GARIN |
| GPI Written Notices | Cleared | 8/18/2021 | ALYSSA N NARCISO |
Contact Information
| Architect | Hersey,, John P; Lic. No.: C25560 | 8067 WILLOW GLEN ROAD LOS ANGELES, CA 90046 |
| Contractor | Backbreaker Inc; Lic. No.: 877306-B | 25520 AVENUE STANFORD STE 304 VALENCIA, CA 91355 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Zhuang,, Wenbin; Lic. No.: S5236 | 205 S CHAPEL AVE #D-1 ALHAMBRA, CA 91801 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/1/2021 | Conditional Approval | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 10/4/2021 | Corrections Issued | JOHN KIDWELL |
| Deputy Drilled-In Anchors | 10/6/2021 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 10/7/2021 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 10/15/2021 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 10/15/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2021 | Partial Approval | JOHN KIDWELL |
| HVAC-Rough | 1/14/2022 | Approved | JOHN KIDWELL |
| ELECTRICAL-Rough | 1/21/2022 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2022 | Approved | JOHN KIDWELL |
| Green Building Rough | 1/27/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 1/27/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Sewer | 1/27/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 2/1/2022 | Corrections Issued | JOHN KIDWELL |
| PLUMBING-Rough | 2/3/2022 | Approved | JOHN KIDWELL |
| Sewer | 2/3/2022 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 2/18/2022 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 2/18/2022 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 2/18/2022 | Approved | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 2/18/2022 | Approved | JOHN KIDWELL |
| Shower Pan | 2/24/2022 | Approved | RYAN SALAZAR |
| Insulation | 3/1/2022 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 3/4/2022 | Partial Approval | BRENDAN LOONEY |
| Interior/Exterior Lathing | 3/8/2022 | Partial Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 3/22/2022 | Corrections Issued | STEPHANIE SWANSON |
| Drywall Nailing | 3/22/2022 | Not Ready for Inspection | STEPHANIE SWANSON |
| Deputy Wood Construction | 3/23/2022 | Approved | MICHAEL PELHAM |
| Drywall Nailing | 3/25/2022 | Approved | JOHN KIDWELL |
| ELECTRICAL-Final | 10/27/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Gas Test | 10/27/2022 | Approved | JUAN VALENZUELA |
| HVAC-Final | 10/27/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| PLUMBING-Final | 10/27/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 10/27/2022 | SGSOV Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 3/3/2023 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 3/3/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Final | 3/3/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Green Building Final | 3/3/2023 | Approved | OGANES TARAKHCHYAN |
| Grounding or Bonding | 3/3/2023 | Partial Approval | OGANES TARAKHCHYAN |
| HVAC-Final | 3/3/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| PLUMBING-Final | 3/3/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Smoke Detectors | 3/3/2023 | Approved | OGANES TARAKHCHYAN |
| Special/Order Compliance | 3/14/2023 | Partial Approval | KENNETH NAGLE |
| ELECTRICAL-Final | 3/16/2023 | Approved | OGANES TARAKHCHYAN |
| Final | 3/16/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Grounding or Bonding | 3/16/2023 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 3/16/2023 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 3/16/2023 | Approved | OGANES TARAKHCHYAN |
| Final | 3/17/2023 | OK to Issue CofO | OGANES TARAKHCHYAN |