6340 N COSTELLO AVE 91401
Certificate Information: 6340 N COSTELLO AVE 91401
- Application / Permit
- 21014-20000-00028
- Plan Check / Job No.
- B21VN00064
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX DETACHED GARAGE INTO ACCESSORY DWELLING UNIT W/ ADDITION (18'X18') PER ORD #186,481.
- Permit Issued
- Issued on 3/25/2021
- Issuing Office
- Current Status
- CofO Issued on 6/8/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/15/2021 | HAYATO TSUCHIYA |
| Corrections Issued | 1/18/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 2/23/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 3/9/2021 | HAYATO TSUCHIYA |
| Plan Check Approved | 3/25/2021 | HAYATO TSUCHIYA |
| Issued | 3/25/2021 | APPLICANT |
| Building Plans Picked Up | 4/9/2021 | APPLICANT |
| CofO in Progress | 5/12/2022 | MICHAEL TEMPLE |
| CofO Issued | 6/8/2022 | MICHAEL SMITH |
| Permit Finaled | 6/8/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/22/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/22/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 1/22/2021 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 3/23/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/2/2021 | Partial Approval | AMY COLIN |
| Deputy Drilled-In Anchors | 9/7/2021 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 9/8/2021 | Corrections Issued | RICHARD DOCKUS |
| ELECTRICAL-Rough | 9/16/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| Footing/Foundation/Slab | 9/16/2021 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 9/16/2021 | Partial Approval | RICHARD DOCKUS |
| Sewer | 9/16/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| Deputy Drilled-In Anchors | 9/20/2021 | Approved | RICHARD DOCKUS |
| Gas Test | 9/20/2021 | Partial Approval | RICHARD DOCKUS |
| PLUMBING-Final | 9/20/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| Sewer | 9/20/2021 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 10/20/2021 | Partial Approval | RICHARD DOCKUS |
| Green Building Rough | 10/20/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| Wood Frame | 10/20/2021 | Partial Approval | RICHARD DOCKUS |
| Gas Test | 11/16/2021 | Corrections Issued | RICHARD DOCKUS |
| PLUMBING-Rough | 11/16/2021 | Corrections Issued | RICHARD DOCKUS |
| ELECTRICAL-Rough | 11/24/2021 | Corrections Issued | RICHARD DOCKUS |
| Gas Test | 11/24/2021 | Partial Approval | RICHARD DOCKUS |
| HVAC-Rough | 11/24/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Rough | 11/24/2021 | Approved | RICHARD DOCKUS |
| Insulation | 12/1/2021 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 12/1/2021 | Partial Approval | JACK KARGODORIAN |
| Drywall Nailing | 12/7/2021 | Corrections Issued | RICHARD DOCKUS |
| Green Building Rough | 12/7/2021 | Approved | RICHARD DOCKUS |
| HVAC-Rough | 12/8/2021 | Approved | RICHARD DOCKUS |
| Drywall Nailing | 12/14/2021 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 12/14/2021 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 4/22/2022 | Corrections Issued | RICHARD DOCKUS |
| ELECTRICAL-Final | 4/22/2022 | Corrections Issued | RICHARD DOCKUS |
| Green Building Final | 4/22/2022 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 4/22/2022 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 4/22/2022 | Corrections Issued | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 5/6/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 5/6/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Final | 5/6/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Final | 5/6/2022 | Approved | RICHARD DOCKUS |
| Smoke Detectors | 5/6/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 5/11/2022 | Approved | MICHAEL TEMPLE |
| Final | 5/11/2022 | OK to Issue CofO | MICHAEL TEMPLE |
| HVAC-Final | 5/11/2022 | Approved | MICHAEL TEMPLE |