20405-20407 W MAYALL ST 91311
Certificate Information: 20405-20407 W MAYALL ST 91311
- Application / Permit
- 21014-20000-00025
- Plan Check / Job No.
- B21VN00051
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT WITH 2ND FLR ADDITION PER LAMC 12.22 A.33(c) AND (e), ADDITION TO (E) SINGLE FAMILY DWELLING, ADD PORCH. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 3/17/2022
- Issuing Office
- Current Status
- Issued on 3/17/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2021 | COLIN LOREDO |
| Corrections Issued | 2/1/2021 | COLIN LOREDO |
| Quality Review Completed | 2/16/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 6/21/2021 | APPLICANT |
| Applicant returned to address corrections | 2/1/2022 | COLIN LOREDO |
| Applicant returned to address corrections | 2/10/2022 | COLIN LOREDO |
| Plan Check Approved | 3/17/2022 | COLIN LOREDO |
| Issued | 3/17/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/24/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 2/24/2021 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 6/21/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 6/22/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/18/2022 | Approved | JEFFREY PARD |
| Footing/Foundation/Slab | 5/31/2022 | Corrections Issued | JEFFREY PARD |
| PLUMBING-Rough | 5/31/2022 | Partial Approval | JEFFREY PARD |
| Deputy Drilled-In Anchors | 6/2/2022 | Conditional Approval | KRISTEN CAUSEY |
| Footing/Foundation/Slab | 6/6/2022 | Partial Approval | JEFFREY PARD |
| Footing/Foundation/Slab | 6/13/2022 | Approved | JEFFREY PARD |
| Deputy Drilled-In Anchors | 6/14/2022 | Conditional Approval | KRISTEN CAUSEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2022 | Partial Approval | JEFFREY PARD |
| Wood Frame | 6/28/2022 | Partial Approval | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2022 | Partial Approval | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 9/26/2022 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 9/26/2022 | Approved | JEFFREY BULL |
| Green Building Rough | 9/26/2022 | Approved | JEFFREY BULL |
| HVAC-Rough | 9/26/2022 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 9/26/2022 | Partial Approval | JEFFREY BULL |
| Rough-Elec/Plmb/HVAC | 9/26/2022 | Approved | JEFFREY BULL |
| Sewer | 9/26/2022 | Not Ready for Inspection | JEFFREY BULL |
| Insulation | 10/3/2022 | Not Ready for Inspection | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 10/3/2022 | Partial Inspection | JOHN KIDWELL |
| Shower Pan | 10/3/2022 | Not Ready for Inspection | KRISTEN CAUSEY |
| Insulation | 10/5/2022 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 10/5/2022 | Not Ready for Inspection | KRISTEN CAUSEY |
| Shower Pan | 10/5/2022 | Approved | KRISTEN CAUSEY |
| Drywall Nailing | 10/18/2022 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 10/18/2022 | Approved | KRISTEN CAUSEY |
| Sewer | 10/18/2022 | Partial Approval | KRISTEN CAUSEY |
| Smoke Detectors | 9/14/2023 | Not Ready for Inspection | JOHN KIDWELL |
| Final | 12/1/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2023 | Approved | DAVID SCANTLIN |
| Green Building Final | 12/1/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 12/1/2023 | SGSOV Not Ready | DAVID SCANTLIN |
| Smoke Detectors | 12/1/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Wood Frame | 12/1/2023 | Not Ready for Inspection | DAVID SCANTLIN |