12469 W GREENE AVE 90066

Certificate Information: 12469 W GREENE AVE 90066

Application / Permit
21014-10004-04825
Plan Check / Job No.
B24VN21802
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: SUPPLEMENTAL TO PERMIT # 21014-20001-04825. REMODEL OF EXISTING ONE-STORY SINGLE-FAMILY DWELLING WITH CHANGE IN HEIGHT AND CHANGE OF ARCHITECT.
Permit Issued
Issued on 12/9/2024
Issuing Office
Current Status
Permit Finaled on 9/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/1/2024 APPLICANT
Assigned to Plan Check Engineer 11/4/2024 ZAW HAN
Corrections Issued 11/5/2024 ZAW HAN
Applicant returned to address corrections 11/14/2024 ZAW HAN
Plan Check Approved 12/8/2024 ZAW HAN
Issued 12/9/2024 APPLICANT
Permit Finaled 9/11/2025 RUBEN RIVAS
Permit Finaled 9/12/2025 DAVID FEILER

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/7/2024 VLADIMIR ARUTYUNYAN
Roof/Waste drainage to street Cleared 11/7/2024 VLADIMIR ARUTYUNYAN
ZA Case Cleared 11/18/2024 ROSALINDA MEZA
Specific Plan Cleared 12/3/2024 HAMID GHAEMMAGHAMI

Contact Information

Architect Hamilton,, John Patrick; Lic. No.: NA28865       ,
Contractor Owner-Builder       ,
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/16/2024 Approved MICHAEL ALLEN
Footing/Foundation/Slab 12/16/2024 Corrections Issued MICHAEL ALLEN
Footing/Foundation/Slab 12/23/2024 Approved MICHAEL ALLEN
Wood Frame 12/31/2024 Partial Approval MICHAEL ALLEN
PLUMBING-Rough 1/3/2025 Partial Approval MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 1/8/2025 Partial Approval JESUS RODRIGUEZ
Insulation 1/8/2025 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 1/29/2025 Approved MICHAEL ALLEN
ELECTRICAL-Rough 2/18/2025 Corrections Issued MICHAEL ALLEN
Gas Test 2/18/2025 Approved MICHAEL ALLEN
HVAC-Rough 2/18/2025 Approved MICHAEL ALLEN
PLUMBING-Rough 2/18/2025 Corrections Issued MICHAEL ALLEN
Wood Frame 2/18/2025 Approved MICHAEL ALLEN
ELECTRICAL-Rough 2/21/2025 Approved MICHAEL ALLEN
Interior/Exterior Lathing 2/21/2025 Partial Approval MICHAEL ALLEN
PLUMBING-Rough 2/21/2025 Approved MICHAEL ALLEN
Shower Pan 2/21/2025 Approved MICHAEL ALLEN
Insulation 2/27/2025 Approved MICHAEL ALLEN
Drywall Nailing 3/4/2025 Approved MICHAEL ALLEN
Interior/Exterior Lathing 3/4/2025 Approved MICHAEL ALLEN
Final 4/22/2025 Not Ready for Inspection RUBEN RIVAS
Smoke Detectors 4/22/2025 Approved RUBEN RIVAS
Final 4/28/2025 Partial Approval RUBEN RIVAS
Final 5/5/2025 Not Ready for Inspection RUBEN RIVAS
Special/Order Compliance 5/8/2025 Corrections Issued DAVID FEILER
Service/Power Release 5/9/2025 Approved DAVID FEILER
Final 9/11/2025 Permit Finaled RUBEN RIVAS