1174 S WINDSOR BLVD 90019

Certificate Information: 1174 S WINDSOR BLVD 90019

Application / Permit
21014-10002-03739
Plan Check / Job No.
B22LA14680
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePLAN. SUPPLEMENTAL TO PERMIT #21016-10000-25038 TO REVISE INTERIOR LAYOUT, ADDITION AT KITCHEN AREA, REPLACE WINDOWS, REINFORCE EXISTING FRAMING THROUGHOUT.
Permit Issued
Issued on 9/22/2022
Issuing Office
Current Status
Permit Finaled on 12/18/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/26/2022 APPLICANT
Assigned to Plan Check Engineer 7/27/2022 LAMAR DAVIS
Plan Check Approved 9/8/2022 LAMAR DAVIS
Issued 9/22/2022 APPLICANT
Permit Finaled 12/11/2023 WILLIAM MICHALAK

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/5/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 8/8/2022 CINDY QI
HPOZ Cleared 8/31/2022 AMANDA KAINER
Miscellaneous Cleared 8/31/2022 AMANDA KAINER
Miscellaneous Cleared 8/31/2022 AMANDA KAINER

Contact Information

Contractor J T S P Inc; Lic. No.: 1039978-B 1107 FAIR OAKS AVE #336      SOUTH PASADENA, CA 91030
Engineer Yu,, Kunyoung; Lic. No.: C66880 22812 ERIEL AVE      TORRANCE, CA 90505

Inspector Information

LUIS CORRAL, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
DONALD WONG, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
KIM DOEPPING, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM MICHALAK, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/28/2022 Not Ready for Inspection STUART CHAPMAN
Pre-Inspection 9/29/2022 Corrections Issued GLEN RAND
FLOOD-Elevation Certificate 10/17/2022 Partial Approval GLEN RAND
Footing/Foundation/Slab 10/17/2022 Corrections Issued GLEN RAND
METHANE-Barrier 10/17/2022 Approved GLEN RAND
METHANE-Subgrade 10/17/2022 Approved GLEN RAND
Deputy Drilled-In Anchors 11/21/2022 Approved GLEN RAND
Rough-Elec/Plmb/HVAC 12/14/2022 Corrections Issued GLEN RAND
Sewer 12/14/2022 Partial Approval GLEN RAND
Underground Mechanical 12/14/2022 Partial Approval GLEN RAND
Deputy Drilled-In Anchors 12/23/2022 Approved GLEN RAND
BUILDING-Rough-Frame 12/28/2022 Corrections Issued GLEN RAND
ELECTRICAL-Rough 12/28/2022 Approved GLEN RAND
FLOOD-Proofing Certificate 12/28/2022 Corrections Issued GLEN RAND
Green Building Rough 12/28/2022 Approved GLEN RAND
METHANE-Rough 12/28/2022 Approved GLEN RAND
Floor/Roof Diaphrgm/Shear Wall 2/1/2023 Corrections Issued GLEN RAND
BUILDING-Rough-Frame 3/13/2023 Conditional Approval GLEN RAND
Interior/Exterior Lathing 3/17/2023 Partial Approval GLEN RAND
Interior/Exterior Lathing 3/24/2023 Corrections Issued WILLIAM MICHALAK
Insulation 4/4/2023 Approved GLEN RAND
Interior/Exterior Lathing 4/4/2023 Approved GLEN RAND
Drywall Nailing 4/26/2023 Approved GLEN RAND
Deputy Drilled-In Anchors 10/6/2023 Approved WILLIAM MICHALAK
BUILDING-Rough-Frame 11/14/2023 Not Ready for Inspection WILLIAM MICHALAK
FLOOD-Elevation Certificate 11/14/2023 Not Ready for Inspection WILLIAM MICHALAK
FLOOD-Proofing Certificate 11/14/2023 Not Ready for Inspection WILLIAM MICHALAK
Final 11/14/2023 Not Ready for Inspection WILLIAM MICHALAK
Footing/Foundation/Slab 11/14/2023 Not Ready for Inspection WILLIAM MICHALAK
Green Building Final 11/14/2023 Not Ready for Inspection WILLIAM MICHALAK
Smoke Detectors 11/14/2023 Approved WILLIAM MICHALAK
Interior/Exterior Lathing 11/28/2023 Not Ready for Inspection WILLIAM MICHALAK
Interior/Exterior Lathing 12/1/2023 Approved WILLIAM MICHALAK
BUILDING-Rough-Frame 12/11/2023 Approved WILLIAM MICHALAK
FLOOD-Elevation Certificate 12/11/2023 Approved WILLIAM MICHALAK
FLOOD-Proofing Certificate 12/11/2023 Approved WILLIAM MICHALAK
Final 12/11/2023 Permit Finaled WILLIAM MICHALAK
Footing/Foundation/Slab 12/11/2023 Approved WILLIAM MICHALAK
Green Building Final 12/11/2023 Approved WILLIAM MICHALAK