1 E NORTHSTAR ST 1-15 90292

Certificate Information: 1 E NORTHSTAR ST 1-15 90292

Application / Permit
21014-10002-00767
Plan Check / Job No.
B22LA20873
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(35) Condo-Multi Family
Work Description
Supplemental permit to 21014-10000-00767 to change window for unit 305 with an operable window where the opening will not allow a 4-inch diameter sphere to pass through the opening when the window is in its lagest opened position per 1015.8 (1). ** No new openings- window changes were permitted under permit no. 22016-10000-24273
Permit Issued
Issued on 10/17/2022
Issuing Office
Metro
Current Status
Permit Finaled on 1/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Plan Check Approved 10/17/2022 KESETE HAREGOT
Issued 10/17/2022 APPLICANT
Permit Finaled 1/26/2024 FARHAD DADBIN

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Ikon Builders Inc; Lic. No.: 966760-B 32158 CAMINO CAPISTRANO A 336      SAN JUAN CAPISTRANO, CA 92675
Engineer Hokama,, Michael Sigueo; Lic. No.: S4505 4 ST JUST AVE      LADERA RANCH, CA 92694

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Insulation 11/30/2022 Partial Approval GRANT WOODS
Drywall Nailing 12/8/2022 Partial Approval GRANT WOODS
Wood Frame 12/8/2022 Partial Approval GRANT WOODS
Drywall Nailing 1/5/2023 Corrections Issued SHAVONNE ESPINOZA
Drywall Nailing 1/18/2023 No Access for Inspection FARHAD DADBIN
Drywall Nailing 1/20/2023 Partial Approval SHAVONNE ESPINOZA
Drywall Nailing 1/24/2023 Approved FARHAD DADBIN
Insulation 1/24/2023 Approved FARHAD DADBIN
Wood Frame 1/24/2023 Partial Approval FARHAD DADBIN
Drywall Nailing 2/22/2023 Approved FARHAD DADBIN
Floor/Roof Diaphrgm/Shear Wall 3/23/2023 Partial Approval SHAVONNE ESPINOZA
Interior/Exterior Lathing 5/2/2023 Not Ready for Inspection FARHAD DADBIN
Insulation 6/5/2023 Approved AMANUEL BERHE
Final 11/17/2023 Not Ready for Inspection AMANUEL BERHE
Final 12/18/2023 Not Ready for Inspection MICHAEL PETRUSKO
Final 1/26/2024 Permit Finaled FARHAD DADBIN