1736 N EUDORA AVE 90744

Certificate Information: 1736 N EUDORA AVE 90744

Application / Permit
21014-10001-06210
Plan Check / Job No.
B22LA13772
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Supplemental to 21014-10000-06210. Revised Structural to be slab on grade construction.
Permit Issued
Issued on 7/25/2022
Issuing Office
Current Status
Permit Finaled on 8/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/14/2022 APPLICANT
Assigned to Plan Check Engineer 7/15/2022 JOSEPH RAFOLS
Plan Check Approved 7/18/2022 JOSEPH RAFOLS
Issued 7/25/2022 APPLICANT
Permit Finaled 8/7/2023 EUGENE CASSIDY

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Yu Yiming; Lic. No.: 973911-B       ,
Engineer Rahman,, Moksudur; Lic. No.: NA69263       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/24/2022 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 9/22/2022 Approved EUGENE CASSIDY
METHANE-Barrier 9/22/2022 Approved EUGENE CASSIDY
METHANE-Subgrade 9/22/2022 Approved EUGENE CASSIDY
PLUMBING-Rough 11/9/2022 Partial Approval EUGENE CASSIDY
Underground Mechanical 11/29/2022 Corrections Issued JOHN KLARIN
ELECTRICAL-Rough 12/6/2022 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 12/6/2022 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 12/30/2022 Corrections Issued EUGENE CASSIDY
Deputy Wood Construction 1/5/2023 Partial Approval EUGENE CASSIDY
Interior/Exterior Lathing 1/26/2023 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 2/9/2023 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 2/9/2023 Approved EUGENE CASSIDY
Interior/Exterior Lathing 2/9/2023 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 2/9/2023 Approved EUGENE CASSIDY
Insulation 2/21/2023 Conditional Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 2/22/2023 Corrections Issued EUGENE CASSIDY
Drywall Nailing 3/1/2023 Approved EUGENE CASSIDY
Interior/Exterior Lathing 3/15/2023 Approved EUGENE CASSIDY
Shower Pan 3/15/2023 Approved EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 4/4/2023 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 4/26/2023 Approved EUGENE CASSIDY
Final 4/26/2023 Corrections Issued EUGENE CASSIDY
Green Building Final 4/26/2023 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 4/26/2023 Approved EUGENE CASSIDY
METHANE-Final 4/26/2023 Approved EUGENE CASSIDY
METHANE-Rough 4/26/2023 Approved EUGENE CASSIDY
Final 6/6/2023 Corrections Issued EUGENE CASSIDY
Green Building Final 6/6/2023 Approved EUGENE CASSIDY
Pre-Inspection 6/26/2023 Approved EUGENE CASSIDY
PLUMBING-Rough 7/13/2023 Approved EUGENE CASSIDY
ELECTRICAL-Final 7/17/2023 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Final 7/17/2023 Approved EUGENE CASSIDY
Final 7/24/2023 Corrections Issued EUGENE CASSIDY
Final 8/7/2023 Permit Finaled EUGENE CASSIDY