7608 S TRUXTON AVE 90045
Certificate Information: 7608 S TRUXTON AVE 90045
- Application / Permit
- 21014-10001-06188
- Plan Check / Job No.
- B22LA23268
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN - SUPPLEMENTAL PERMIT TO PERMIT NO. 21014-10000-06188 TO CAPTURE STRUCTURAL CHANGES, UPDATE STRUCTURAL INVENTORY AND REVISE GREEN SHEETS AND TO REVISE SCOPE OF WORK TO " (N) SFD ADDITION AT FRONT AND REAR, AND ENCLOSE (E) DECK TO CONVERT UNDERFLOOR AREA INTO A RECREATION ROOM RESULTING IN A TWO STORY BUILDING.
- Permit Issued
- Issued on 1/30/2023
- Issuing Office
- Current Status
- Permit Finaled on 6/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/8/2022 | SERGIO GUTIERREZ |
| Corrections Issued | 12/15/2022 | SERGIO GUTIERREZ |
| Quality Review Completed | 12/16/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 12/22/2022 | SERGIO GUTIERREZ |
| Applicant returned to address corrections | 12/28/2022 | MINA HABIB |
| Applicant returned to address corrections | 1/20/2023 | SERGIO GUTIERREZ |
| Plan Check Approved | 1/27/2023 | SERGIO GUTIERREZ |
| Issued | 1/30/2023 | APPLICANT |
| Permit Finaled | 6/21/2023 | BOBBY KEY |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Manesh,, Behnam Abraham; Lic. No.: NA38454 | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Rough-Elec/Plmb/HVAC | 2/2/2023 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 2/9/2023 | Conditional Approval | BOBBY KEY |
| Green Building Rough | 2/9/2023 | Approved | BOBBY KEY |
| Insulation | 2/9/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 2/9/2023 | Approved | BOBBY KEY |
| Drywall Nailing | 3/6/2023 | Conditional Approval | BOBBY KEY |