6226 E MOUNT ANGELUS PL 1-4 90042
Certificate Information: 6226 E MOUNT ANGELUS PL 1-4 90042
- Application / Permit
- 21014-10001-05959
- Plan Check / Job No.
- B21LA22347
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- supplemental permit to 21014-10000-05959 to revise engineering work under new engineer
- Permit Issued
- Issued on 4/17/2023
- Issuing Office
- Current Status
- Permit Finaled on 12/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2022 | JAD BASMA |
| Corrections Issued | 3/18/2022 | JAD BASMA |
| Quality Review Completed | 3/18/2022 | KEN GILL |
| Building Plans Picked Up | 3/23/2022 | APPLICANT |
| Applicant returned to address corrections | 5/25/2022 | JAD BASMA |
| Applicant returned to address corrections | 6/6/2022 | JAD BASMA |
| Plan Check Approved | 1/18/2023 | JAD BASMA |
| Issued | 4/17/2023 | APPLICANT |
| Permit Finaled | 11/27/2024 | LILIANA PORTILLO |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Alpha Structural Inc; Lic. No.: 663409-B | 8334 FOOTHILL BLVD SUNLAND, CA 91040 |
| Contractor | Owner-Builder | , |
| Engineer | Alpha, Structural; Lic. No.: C71535 | 8334 FOOTHILL BLVD SUNLAND, CA 91040 |
| Engineer | David, Li & Associates; Lic. No.: C58075 | 1305 SAN GABRIEL BLVD 101 ROSEMEAD, CA 91770 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/26/2023 | Not Ready for Inspection | AMY COLIN |
| Pre-Inspection | 6/28/2023 | Partial Inspection | AMY COLIN |
| Piling/Pier/Caisson | 7/7/2023 | Approved | AMY COLIN |
| BUILDING-Rough-Frame | 8/22/2023 | Corrections Issued | AMY COLIN |
| ELECTRICAL-Rough | 8/22/2023 | Corrections Issued | AMY COLIN |
| Green Building Rough | 8/22/2023 | Not Ready for Inspection | AMY COLIN |
| Shower Pan | 8/22/2023 | Corrections Issued | AMY COLIN |
| Insulation | 9/5/2023 | Partial Approval | AMY COLIN |
| Drywall Nailing | 9/13/2023 | Partial Approval | AMY COLIN |
| Shower Pan | 9/13/2023 | Approved | AMY COLIN |
| Wood Frame | 9/13/2023 | Partial Approval | AMY COLIN |
| BUILDING-Rough-Frame | 5/6/2024 | Approved | LILIANA PORTILLO |
| Final | 5/6/2024 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 5/6/2024 | Approved | LILIANA PORTILLO |
| Green Building Final | 5/6/2024 | Approved | LILIANA PORTILLO |
| Green Building Rough | 5/6/2024 | Approved | LILIANA PORTILLO |
| Service/Power Release | 5/6/2024 | Not Required | LILIANA PORTILLO |
| Final | 7/18/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 11/27/2024 | Permit Finaled | LILIANA PORTILLO |