3306-3308 S CORINTH AVE 90066
Certificate Information: 3306-3308 S CORINTH AVE 90066
- Application / Permit
- 21014-10001-04880
- Plan Check / Job No.
- B21LA21550
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: SUPPLEMENTAL TO PERMIT 21014-10000-04880 TO CAPTURE ADDITION TO SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 1/4/2022
- Issuing Office
- Current Status
- Permit Finaled on 5/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/22/2021 | MICHAEL LOPEZ |
| Corrections Issued | 11/22/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 12/9/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 12/22/2021 | SELLA BENYAMIN |
| Plan Check Approved | 12/27/2021 | DANIEL YIP |
| Issued | 1/4/2022 | APPLICANT |
| Permit Finaled | 5/29/2025 | WILBER ROSALES |
Permit Application Clearance Information
| Specific Plan | Cleared | 12/2/2021 | FREDDY GARCIA |
| Grading Pre-Inspection | Cleared | 12/8/2021 | VASIL MIHALEV |
| GPI Written Notices | Cleared | 12/16/2021 | MICHAEL LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/20/2021 | RAYMOND MUGAMBWA |
| Roof/Waste drainage to street | Cleared | 12/20/2021 | RAYMOND MUGAMBWA |
| Sewer availability | Cleared | 12/20/2021 | RAYMOND MUGAMBWA |
Contact Information
| Contractor | D U A Build; Lic. No.: 967782-B | 3579 EAST FOOTHILL BLVD #405 PASADENA, CA 91107 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/11/2022 | Approved | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 2/11/2022 | Approved | JOHNNY MIRANDA |
| Sewer | 3/15/2022 | No Access for Inspection | EVAN COOPER |
| PLUMBING-Rough | 3/16/2022 | Partial Approval | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 9/7/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2022 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 9/7/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| MERV13>=Rough | 9/7/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Rough-Elec/Plmb/HVAC | 9/7/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 9/28/2022 | Not Ready for Inspection | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2022 | Partial Approval | ANDREW NAVE |
| HVAC-Rough | 9/28/2022 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 9/28/2022 | Not Ready for Inspection | ANDREW NAVE |
| Insulation | 10/11/2022 | Partial Approval | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 10/11/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Insulation | 10/17/2022 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 11/9/2022 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 11/9/2022 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 11/9/2022 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 11/9/2022 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 11/9/2022 | Approved | JOHNNY MIRANDA |
| Special/Order Compliance | 2/14/2023 | Partial Approval | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 8/31/2023 | Approved | JESUS PINEDA |
| Final | 8/31/2023 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 8/31/2023 | Not Ready for Inspection | JESUS PINEDA |
| MERV13>=Final | 8/31/2023 | Not Ready for Inspection | JESUS PINEDA |
| MERV13>=Rough | 8/31/2023 | Approved | JESUS PINEDA |
| Smoke Detectors | 8/31/2023 | Corrections Issued | JESUS PINEDA |
| Final | 5/29/2025 | Permit Finaled | WILBER ROSALES |
| Green Building Final | 5/29/2025 | Approved | WILBER ROSALES |
| MERV13>=Final | 5/29/2025 | Approved | WILBER ROSALES |
| Smoke Detectors | 5/29/2025 | Approved | WILBER ROSALES |