2255 N BETTY LANE 90210
Certificate Information: 2255 N BETTY LANE 90210
- Application / Permit
- 21014-10001-03130
- Plan Check / Job No.
- B22WL04228
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: UPDATE TO EXISTING APPROVED PERMIT 21014-30000-03130: Interior remodel to kitchen- updating layout and location. Addition of laundry closet, larger master walk-in closet, updated master bathroom. (INTERIOR REMODEL ONLY) Updates to lighting plan.
- Permit Issued
- Issued on 2/6/2023
- Issuing Office
- Current Status
- Permit Finaled on 10/3/2023
Permit Application Status History
| Submitted | 11/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2022 | SUNMIN LEE |
| Corrections Issued | 11/22/2022 | SUNMIN LEE |
| Applicant returned to address corrections | 1/9/2023 | EDWIN ESPIN |
| Plan Check Approved | 1/29/2023 | KHUONG TRUONG |
| Issued | 2/6/2023 | APPLICANT |
| Permit Finaled | 10/2/2023 | STUART CHAPMAN |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Navarro Construction Inc; Lic. No.: 781996-B | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 2/8/2023 | Approved | RAUL BARAJAS |
| HVAC-Rough | 2/8/2023 | Approved | RAUL BARAJAS |
| PLUMBING-Rough | 2/8/2023 | Approved | RAUL BARAJAS |
| Wood Frame | 2/8/2023 | Approved | RAUL BARAJAS |
| Drywall Nailing | 2/14/2023 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 4/18/2023 | Partial Inspection | RAUL BARAJAS |
| Interior/Exterior Lathing | 5/3/2023 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 10/2/2023 | Approved | STUART CHAPMAN |
| Final | 10/2/2023 | Permit Finaled | STUART CHAPMAN |
| Footing/Foundation/Slab | 10/2/2023 | Approved | STUART CHAPMAN |
| Green Building Final | 10/2/2023 | Approved | STUART CHAPMAN |
| Green Building Rough | 10/2/2023 | Approved | STUART CHAPMAN |
| Smoke Detectors | 10/2/2023 | Approved | STUART CHAPMAN |