4257 S MENLO AVE 90037
Certificate Information: 4257 S MENLO AVE 90037
- Application / Permit
- 21014-10001-01783
- Plan Check / Job No.
- B22LA02225
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- SUPPLEMENTAL TO 21014-10000-01783 FOR NEW ADU PER ENGINEER DESIGN 800 SF max New Construction per State Law, CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g))
- Permit Issued
- Issued on 7/22/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 7/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/16/2022 | ZAW HAN |
| Corrections Issued | 2/18/2022 | ZAW HAN |
| Building Plans Picked Up | 2/24/2022 | APPLICANT |
| Plan Check Approved | 6/24/2022 | KHUONG TRUONG |
| Issued | 7/22/2022 | APPLICANT |
| Permit Finaled | 7/23/2024 | SABAS ALONSO |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2022 | CELINA MORENO |
| Sewer availability | Cleared | 3/10/2022 | CELINA MORENO |
| Low Impact Development | Cleared | 4/11/2022 | MICHAEL SCADUTO |
| "Q" conditions | Cleared | 4/14/2022 | MAXFIELD VERMY |
| Construction near power lines | Cleared | 6/9/2022 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 6/16/2022 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Medina,, Armando; Lic. No.: C83911 | 2000 W LINCOLN AVE MONTEBELLO, CA 90640 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/1/2022 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 8/1/2022 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 7/23/2024 | Approved | SABAS ALONSO |
| Drywall Nailing | 7/23/2024 | Approved | SABAS ALONSO |
| Final | 7/23/2024 | Permit Finaled | SABAS ALONSO |
| Footing/Foundation/Slab | 7/23/2024 | Approved | SABAS ALONSO |
| Green Building Final | 7/23/2024 | Approved | SABAS ALONSO |
| Green Building Rough | 7/23/2024 | Approved | SABAS ALONSO |
| Service/Power Release | 7/23/2024 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 7/23/2024 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 7/23/2024 | Not Ready for Inspection | SABAS ALONSO |