727 1/4-1/8 W 73RD ST 90044
Certificate Information: 727 1/4-1/8 W 73RD ST 90044
- Application / Permit
- 21014-10001-01237
- Plan Check / Job No.
- B21LA24516
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. Supplemental to permit 21014-10000-01237 to add second floor and one new ADU on second floor. **see comments
- Permit Issued
- Issued on 8/25/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 6/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2022 | HELEN NGUYEN |
| Corrections Issued | 1/31/2022 | HELEN NGUYEN |
| Applicant returned to address corrections | 2/15/2022 | HELEN NGUYEN |
| Applicant returned to address corrections | 2/21/2022 | HELEN NGUYEN |
| Applicant returned to address corrections | 2/28/2022 | HELEN NGUYEN |
| Applicant returned to address corrections | 4/15/2022 | HELEN NGUYEN |
| Applicant returned to address corrections | 5/10/2022 | HELEN NGUYEN |
| Applicant returned to address corrections | 6/29/2022 | GEORGE ALVAREZ |
| Plan Check Approved | 7/12/2022 | ADAM HEGAZI |
| Issued | 8/25/2022 | APPLICANT |
| Permit Finaled | 6/2/2023 | STUART CHAPMAN |
Permit Application Clearance Information
| Address approval | Cleared | 4/20/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 5/9/2022 | CINDY QI |
| Sewer availability | Cleared | 5/9/2022 | CINDY QI |
| Low Impact Development | Cleared | 6/27/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 7/19/2022 | STEVE MELGAR |
Contact Information
| Architect | Cataldo,, John G; Lic. No.: C10457 | 835 MISSION STREET SOUTH PASADENA, CA 91030 |
| Contractor | V C Construction & Development; Lic. No.: 959583-B | 24132 MEADOW FALLS DRIVE DIAMOND BAR, CA 91765 |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/2/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Excavation/Setback/Form/Re-Bar | 9/16/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Excavation/Setback/Form/Re-Bar | 9/21/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Final | 4/18/2023 | Corrections Issued | LILIANA PORTILLO |
| Drywall Nailing | 6/2/2023 | Approved | STUART CHAPMAN |
| Final | 6/2/2023 | Permit Finaled | STUART CHAPMAN |
| Footing/Foundation/Slab | 6/2/2023 | Approved | STUART CHAPMAN |
| Green Building Final | 6/2/2023 | Approved | STUART CHAPMAN |
| Green Building Rough | 6/2/2023 | Approved | STUART CHAPMAN |
| Smoke Detectors | 6/2/2023 | Approved | STUART CHAPMAN |
| Wood Frame | 6/2/2023 | Approved | STUART CHAPMAN |