1413-1413 1/2 S ORCHARD AVE 90006
Certificate Information: 1413-1413 1/2 S ORCHARD AVE 90006
- Application / Permit
- 21014-10001-01070
- Plan Check / Job No.
- B23LA09688
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- SUPPLEMENTAL PERMIT TO PERMIT NO. 21014 - 10000 - 01070 TO CHANGE ENGINEER OF RECORD AND CHANGE SCOPE OF WORK TO "New 1-Story Duplex (2 ADU's) With Roof Deck. PER CA Govt. Code 65852.2(e)(1)(D) and applicable part 2 of LAMC 12.22 A.33 (c)-(d), (g) " SEE COMMENTS
- Permit Issued
- Issued on 2/27/2024
- Issuing Office
- Current Status
- Permit Finaled on 11/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2023 | SERGIO GUTIERREZ |
| Corrections Issued | 7/10/2023 | SERGIO GUTIERREZ |
| Quality Review Completed | 7/12/2023 | RODOLFO ARIAS |
| Applicant returned to address corrections | 1/3/2024 | SERGIO GUTIERREZ |
| Plan Check Approved | 1/26/2024 | SERGIO GUTIERREZ |
| Issued | 2/27/2024 | APPLICANT |
| Permit Finaled | 11/21/2025 | WILLIAM SIERRA |
Permit Application Clearance Information
| Address approval | Cleared | 10/7/2023 | TERRY PHAN |
| Roof/Waste drainage to street | Cleared | 10/7/2023 | TERRY PHAN |
| Sewer availability | Cleared | 10/7/2023 | TERRY PHAN |
| Eng Process Fee Ord 176,300 | Cleared | 10/10/2023 | TERRY PHAN |
| Hydrant and Access approval | Cleared | 11/7/2023 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/5/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Sewer | 4/5/2024 | Approved | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 4/11/2024 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 5/28/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 5/28/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Rough | 5/28/2024 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 5/28/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 5/28/2024 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 5/28/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Wood Frame | 5/28/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 6/6/2024 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Rough | 6/6/2024 | Approved | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| HVAC-Rough | 6/6/2024 | Corrections Issued | BRENDAN MORELLI |
| Verify Sprinkler Sign Off | 6/6/2024 | Corrections Issued | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 7/8/2024 | Corrections Issued | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 7/8/2024 | Corrections Issued | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2024 | Partial Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 7/8/2024 | Corrections Issued | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 7/8/2024 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 7/25/2024 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 7/25/2024 | Partial Approval | JOSEPH MCGARRY |
| HVAC-Rough | 7/25/2024 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 7/25/2024 | Approved | JOSEPH MCGARRY |
| Rough-Elec/Plmb/HVAC | 7/25/2024 | Partial Approval | JOSEPH MCGARRY |
| Special/Order Compliance | 7/25/2024 | Approved | WILLIAM SIERRA |
| Interior/Exterior Lathing | 8/5/2024 | Partial Approval | WILLIAM SIERRA |
| Insulation | 8/14/2024 | Approved | WILLIAM SIERRA |
| Interior/Exterior Lathing | 8/14/2024 | Partial Approval | WILLIAM SIERRA |
| Shower Pan | 8/14/2024 | Not Ready for Inspection | WILLIAM SIERRA |
| Interior/Exterior Lathing | 8/19/2024 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 8/26/2024 | Corrections Issued | WILLIAM SIERRA |
| Drywall Nailing | 8/28/2024 | No Access for Inspection | WILLIAM SIERRA |
| Drywall Nailing | 9/3/2024 | Approved | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 10/8/2024 | Approved | WILLIAM SIERRA |
| PLUMBING-Final | 10/30/2024 | Corrections Issued | JOHN QUINTANILLA |
| ELECTRICAL-Final | 2/11/2025 | Corrections Issued | WILLIAM SIERRA |
| PLUMBING-Final | 2/11/2025 | Corrections Issued | WILLIAM SIERRA |
| BUILDING-Rough-Frame | 3/5/2025 | Approved | WILLIAM SIERRA |
| ELECTRICAL-Final | 3/5/2025 | Corrections Issued | WILLIAM SIERRA |
| Final | 3/5/2025 | Corrections Issued | WILLIAM SIERRA |
| Green Building Final | 3/5/2025 | Corrections Issued | WILLIAM SIERRA |
| HVAC-Final | 3/5/2025 | Corrections Issued | WILLIAM SIERRA |
| PLUMBING-Final | 3/5/2025 | Corrections Issued | WILLIAM SIERRA |
| Service/Power Release | 3/5/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| Smoke Detectors | 3/5/2025 | Partial Approval | WILLIAM SIERRA |
| ELECTRICAL-Final | 9/16/2025 | Corrections Issued | WILLIAM SIERRA |
| Final | 9/16/2025 | Corrections Issued | WILLIAM SIERRA |
| Green Building Final | 9/16/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| HVAC-Final | 9/16/2025 | Corrections Issued | WILLIAM SIERRA |
| PLUMBING-Final | 9/16/2025 | Approved | WILLIAM SIERRA |
| Service/Power Release | 9/16/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| Smoke Detectors | 9/16/2025 | Approved | WILLIAM SIERRA |
| ELECTRICAL-Final | 10/8/2025 | Approved | WILLIAM SIERRA |
| Final | 10/8/2025 | Corrections Issued | WILLIAM SIERRA |
| Green Building Final | 10/8/2025 | Corrections Issued | WILLIAM SIERRA |
| HVAC-Final | 10/8/2025 | Approved | WILLIAM SIERRA |
| PLUMBING-Final | 10/8/2025 | Approved | WILLIAM SIERRA |
| Service/Power Release | 10/8/2025 | Corrections Issued | WILLIAM SIERRA |
| ELECTRICAL-Final | 11/21/2025 | Approved | WILLIAM SIERRA |
| Final | 11/21/2025 | Permit Finaled | WILLIAM SIERRA |
| Green Building Final | 11/21/2025 | Approved | WILLIAM SIERRA |
| HVAC-Final | 11/21/2025 | Approved | WILLIAM SIERRA |
| PLUMBING-Final | 11/21/2025 | Approved | WILLIAM SIERRA |
| Service/Power Release | 11/21/2025 | Approved | WILLIAM SIERRA |