5346 W SANCHEZ DR 90008

Certificate Information: 5346 W SANCHEZ DR 90008

Application / Permit
21014-10001-01028
Plan Check / Job No.
B23LA09710
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SUPPLEMENTAL PERMIT FOR AN APPROVED 2ND STORY ADDITION VIA PERMIT #21014-10000-01028 CHANGE THE DESING OF THE FRONT ELEVATION WITH SFD AND NEW DECK ADDITION.
Permit Issued
Issued on 7/5/2023
Issuing Office
Metro
Current Status
Permit Finaled on 9/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/24/2023 APPLICANT
Assigned to Plan Check Engineer 5/25/2023 SUNMIN LEE
Corrections Issued 5/27/2023 SUNMIN LEE
Quality Review Completed 5/31/2023 KEN GILL
Building Plans Picked Up 6/1/2023 APPLICANT
Applicant returned to address corrections 6/9/2023 SUNMIN LEE
Applicant returned to address corrections 6/15/2023 SUNMIN LEE
Plan Check Approved 6/30/2023 SUNMIN LEE
Issued 7/5/2023 APPLICANT
Permit Finaled 9/22/2025 BRENDAN MORELLI

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Maalouf,, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 11/1/2023 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 11/1/2023 Partial Approval ANTHONY EGSON
HVAC-Rough 11/1/2023 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 11/1/2023 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 11/8/2023 Not Ready for Inspection ANTHONY EGSON
HVAC-Rough 11/8/2023 Approved ANTHONY EGSON
PLUMBING-Rough 11/8/2023 Approved ANTHONY EGSON
BUILDING-Rough-Frame 11/15/2023 No Access for Inspection ANTHONY EGSON
Green Building Rough 11/15/2023 No Access for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 12/6/2023 Partial Approval ANTHONY EGSON
BUILDING-Rough-Frame 12/11/2023 Partial Approval ANTHONY EGSON
Green Building Rough 12/11/2023 Not Ready for Inspection ANTHONY EGSON
Wood Frame 12/11/2023 Not Ready for Inspection ANTHONY EGSON
Interior/Exterior Lathing 12/20/2023 Not Ready for Inspection BRENDAN MORELLI
Shower Pan 3/15/2024 Corrections Issued BRENDAN MORELLI
Green Building Rough 3/27/2024 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 3/27/2024 Approved ALIZAH MAYAGOITIA
Shower Pan 3/27/2024 Approved ALIZAH MAYAGOITIA
Drywall Nailing 4/5/2024 Not Ready for Inspection JOSH MEISTER
Drywall Nailing 4/9/2024 Approved JOSH MEISTER
BUILDING-Rough-Frame 9/18/2025 Approved LUIS CASTRO
Footing/Foundation/Slab 9/18/2025 Approved LUIS CASTRO
Final 9/22/2025 Permit Finaled BRENDAN MORELLI
Green Building Final 9/22/2025 Approved BRENDAN MORELLI
Smoke Detectors 9/22/2025 Approved BRENDAN MORELLI