12633 W ADMIRAL AVE 90066
Certificate Information: 12633 W ADMIRAL AVE 90066
- Application / Permit
- 21014-10000-06496
- Plan Check / Job No.
- B21LA24430
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED TWO CAR GARAGE (18x20 per 1954VE11282) WITH (N) ADDITION TO A 1-STORY 433 SQFT ADU PER ORDINANCE.
- Permit Issued
- Issued on 5/31/2022
- Issuing Office
- Current Status
- CofO Issued on 9/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/5/2022 | MINA HABILI |
| Corrections Issued | 1/6/2022 | MINA HABILI |
| Plan Check Approved | 4/1/2022 | JOSEPH RAFOLS |
| Building Plans Picked Up | 4/8/2022 | APPLICANT |
| Issued | 5/31/2022 | APPLICANT |
| CofO in Progress | 8/30/2023 | HERBERT GIRON |
| Permit Finaled | 9/6/2023 | DANIEL ORRANTE |
| CofO Issued | 9/6/2023 | DANIEL ORRANTE |
| Permit Finaled | 9/6/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 1/15/2022 | ANDREW SLUSSER |
| Roof/Waste drainage to street | Cleared | 1/15/2022 | ANDREW SLUSSER |
| Eng Process Fee Ord 176,300 | Cleared | 1/29/2022 | ANDREW SLUSSER |
| Sewer availability | Cleared | 1/29/2022 | ANDREW SLUSSER |
| Specific Plan | Cleared | 3/29/2022 | PEDRO AYALA |
Contact Information
| Architect | Thibodeau,, Robert E; Lic. No.: C25585 | 812 LINCOLN BLVD VENICE, CA 90291 |
| Contractor | Lyons Glenn Construction Inc; Lic. No.: 640172-B | 1335 APPLETON WAY VENICE, CA 90291 |
| Engineer | Goodman,, Harvey Allan; Lic. No.: C15900 | 834 17TH STREET SANTA MONICA, CA 90403 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 7/18/2022 | Partial Approval | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 7/18/2022 | Partial Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 7/18/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| METHANE-Barrier | 7/18/2022 | Approved | JESUS RODRIGUEZ |
| METHANE-Subgrade | 7/18/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 7/18/2022 | Partial Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 8/2/2022 | Partial Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 8/2/2022 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2022 | Corrections Issued | HERBERT GIRON |
| Green Building Rough | 9/26/2022 | Not Ready for Inspection | HERBERT GIRON |
| METHANE-Rough | 9/26/2022 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2022 | Approved | HERBERT GIRON |
| Green Building Rough | 9/28/2022 | Not Ready for Inspection | HERBERT GIRON |
| HVAC-Rough | 10/20/2022 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 10/20/2022 | Approved | HERBERT GIRON |
| Shower Pan | 10/20/2022 | Approved | HERBERT GIRON |
| Underground Mechanical | 10/20/2022 | Corrections Issued | HERBERT GIRON |
| Sewer | 10/26/2022 | Approved | HERBERT GIRON |
| Underground Mechanical | 10/26/2022 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 11/2/2022 | Approved | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 11/14/2022 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 12/6/2022 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 2/1/2023 | Approved | HERBERT GIRON |
| Green Building Rough | 2/1/2023 | Approved | HERBERT GIRON |
| Insulation | 2/1/2023 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 2/1/2023 | Approved | HERBERT GIRON |
| Drywall Nailing | 2/8/2023 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 2/21/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 6/7/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 6/7/2023 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 6/7/2023 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 6/7/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 7/5/2023 | Approved | HERBERT GIRON |
| Final | 7/5/2023 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 7/5/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 7/5/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 7/5/2023 | Approved | HERBERT GIRON |
| Final | 8/15/2023 | Corrections Issued | HERBERT GIRON |
| Final | 8/30/2023 | OK to Issue CofO | HERBERT GIRON |