15556 W HIGH KNOLL ROAD 91436

Certificate Information: 15556 W HIGH KNOLL ROAD 91436

Application / Permit
21014-10000-06480
Plan Check / Job No.
B21LA24361
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2ND STORY ADDITION TO EXISTING SINGLE FAMILY DWELLING
Permit Issued
Issued on 8/5/2022
Issuing Office
Metro
Current Status
CofO Issued on 7/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/29/2021 APPLICANT
Assigned to Plan Check Engineer 1/13/2022 CRYSTEL MAALOUF
Corrections Issued 1/24/2022 CRYSTEL MAALOUF
Quality Review Completed 2/3/2022 SEAN DANG
Building Plans Picked Up 2/9/2022 APPLICANT
Applicant returned to address corrections 6/24/2022 CRYSTEL MAALOUF
Plan Check Approved 7/27/2022 CRYSTEL MAALOUF
Issued 8/5/2022 APPLICANT
CofO in Progress 10/25/2024 THOMAS FINNILA
CofO in Progress 1/6/2025 THOMAS FINNILA
CofO in Progress 2/19/2025 THOMAS FINNILA
Permit Finaled 7/18/2025 DANIEL ORRANTE
CofO Issued 7/18/2025 DANIEL ORRANTE
Permit Finaled 7/18/2025 DANIEL ORRANTE

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 2/3/2022 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 2/3/2022 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 2/3/2022 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 2/3/2022 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 2/3/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/4/2022 CARLOS AGUILERA
Sewer availability Cleared 2/4/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 4/19/2022 DWIGHT SANKEY
Low Impact Development Cleared 6/3/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 6/6/2022 CARLOS AGUILERA
GPI Written Notices Cleared 7/27/2022 CRYSTEL MAALOUF
Grading Pre-Inspection Cleared 7/27/2022 CRYSTEL MAALOUF

Contact Information

Architect Kerr,, Robert E; Lic. No.: C28038 2551 S BUNDY DRIVE      LOS ANGELES, CA 90064
Contractor Vancrest Construction Corp; Lic. No.: 393800-B 7171 NORTH FIGUEROA STREET      LOS ANGELES, CA 90042
Engineer Mahlow,, Elizabeth Joy Johnson; Lic. No.: C80463 600 WILSHIRE BLVD   SUITE 760    LOS ANGELES, CA 90065

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/15/2022 Approved VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 10/11/2022 Partial Approval VINCENT HANLEY
Piling/Pier/Caisson 10/11/2022 Approved VINCENT HANLEY
Pre-Inspection 10/11/2022 Approved VINCENT HANLEY
Deputy Reinf. Concrete 10/13/2022 Approved VINCENT HANLEY
PLUMBING-Rough 12/9/2022 Partial Approval VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 12/16/2022 Partial Approval DAVID SANDOVAL
Footing/Foundation/Slab 12/16/2022 Approved DAVID SANDOVAL
Deputy Steel/Welding 2/9/2023 Approved VINCENT HANLEY
Deputy Steel/Welding 2/10/2023 Approved VINCENT HANLEY
Deputy Steel/Welding 2/14/2023 Approved VINCENT HANLEY
Deputy Steel/Welding 2/16/2023 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 3/10/2023 Partial Approval VINCENT HANLEY
Wood Frame 3/10/2023 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 4/20/2023 Partial Approval VINCENT HANLEY
Wood Frame 5/8/2023 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 6/5/2023 Partial Approval VINCENT HANLEY
Wood Frame 6/5/2023 Partial Approval VINCENT HANLEY
PLUMBING-Rough 8/17/2023 Approved MORRIS JACKSON
ELECTRICAL-Rough 8/18/2023 Approved JOHN KIDWELL
HVAC-Rough 8/18/2023 Corrections Issued JOHN KIDWELL
HVAC-Rough 8/31/2023 Approved VINCENT HANLEY
Sewer 9/15/2023 Partial Approval VINCENT HANLEY
Service/Power Release 9/18/2023 Approved VINCENT HANLEY
Service/Power Release 9/19/2023 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 10/3/2023 Partial Approval VINCENT HANLEY
Interior/Exterior Lathing 10/19/2023 Not Ready for Inspection VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 11/13/2023 Partial Approval VINCENT HANLEY
Insulation 11/13/2023 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 12/7/2023 Partial Approval VINCENT HANLEY
Green Building Rough 12/7/2023 Approved VINCENT HANLEY
Insulation 12/7/2023 Partial Approval VINCENT HANLEY
Interior/Exterior Lathing 12/7/2023 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 12/26/2023 Approved VINCENT HANLEY
Green Building Final 12/26/2023 Approved VINCENT HANLEY
Interior/Exterior Lathing 12/26/2023 Approved VINCENT HANLEY
MERV13>=Rough 12/26/2023 Approved VINCENT HANLEY
Shower Pan 12/26/2023 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 12/26/2023 Approved VINCENT HANLEY
Drywall Nailing 12/29/2023 Approved VINCENT HANLEY
Wood Frame 1/11/2024 Approved VINCENT HANLEY
Pre-Inspection 3/28/2024 Approved VINCENT HANLEY
Service/Power Release 4/19/2024 Approved VINCENT HANLEY
Sewer 5/20/2024 Approved JEFFREY BULL
Gas Test 6/5/2024 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 6/5/2024 SGSOV Approved MORRIS JACKSON
HVAC-Final 6/14/2024 Approved THOMAS FINNILA
ELECTRICAL-Final 8/2/2024 Partial Approval THOMAS FINNILA
Gas Test 8/2/2024 Approved THOMAS FINNILA
PLUMBING-Final 8/2/2024 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 8/30/2024 Approved ALEXANDER HANDY
PLUMBING-Final 8/30/2024 Approved ALEXANDER HANDY
Final 10/18/2024 Corrections Issued THOMAS FINNILA
MERV13>=Final 10/18/2024 Approved THOMAS FINNILA
Smoke Detectors 10/18/2024 Approved THOMAS FINNILA
Final 10/24/2024 Not Ready for Inspection THOMAS FINNILA
Final 1/14/2025 Corrections Issued THOMAS FINNILA
Final 2/18/2025 OK to Issue CofO THOMAS FINNILA