15556 W HIGH KNOLL ROAD 91436
Certificate Information: 15556 W HIGH KNOLL ROAD 91436
- Application / Permit
- 21014-10000-06480
- Plan Check / Job No.
- B21LA24361
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2ND STORY ADDITION TO EXISTING SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 8/5/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2022 | CRYSTEL MAALOUF |
| Corrections Issued | 1/24/2022 | CRYSTEL MAALOUF |
| Quality Review Completed | 2/3/2022 | SEAN DANG |
| Building Plans Picked Up | 2/9/2022 | APPLICANT |
| Applicant returned to address corrections | 6/24/2022 | CRYSTEL MAALOUF |
| Plan Check Approved | 7/27/2022 | CRYSTEL MAALOUF |
| Issued | 8/5/2022 | APPLICANT |
| CofO in Progress | 10/25/2024 | THOMAS FINNILA |
| CofO in Progress | 1/6/2025 | THOMAS FINNILA |
| CofO in Progress | 2/19/2025 | THOMAS FINNILA |
| Permit Finaled | 7/18/2025 | DANIEL ORRANTE |
| CofO Issued | 7/18/2025 | DANIEL ORRANTE |
| Permit Finaled | 7/18/2025 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 2/3/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 2/3/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 2/3/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 2/3/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 2/3/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 2/4/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/4/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 4/19/2022 | DWIGHT SANKEY |
| Low Impact Development | Cleared | 6/3/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 6/6/2022 | CARLOS AGUILERA |
| GPI Written Notices | Cleared | 7/27/2022 | CRYSTEL MAALOUF |
| Grading Pre-Inspection | Cleared | 7/27/2022 | CRYSTEL MAALOUF |
Contact Information
| Architect | Kerr,, Robert E; Lic. No.: C28038 | 2551 S BUNDY DRIVE LOS ANGELES, CA 90064 |
| Contractor | Vancrest Construction Corp; Lic. No.: 393800-B | 7171 NORTH FIGUEROA STREET LOS ANGELES, CA 90042 |
| Engineer | Mahlow,, Elizabeth Joy Johnson; Lic. No.: C80463 | 600 WILSHIRE BLVD SUITE 760 LOS ANGELES, CA 90065 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/15/2022 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 10/11/2022 | Partial Approval | VINCENT HANLEY |
| Piling/Pier/Caisson | 10/11/2022 | Approved | VINCENT HANLEY |
| Pre-Inspection | 10/11/2022 | Approved | VINCENT HANLEY |
| Deputy Reinf. Concrete | 10/13/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 12/9/2022 | Partial Approval | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 12/16/2022 | Partial Approval | DAVID SANDOVAL |
| Footing/Foundation/Slab | 12/16/2022 | Approved | DAVID SANDOVAL |
| Deputy Steel/Welding | 2/9/2023 | Approved | VINCENT HANLEY |
| Deputy Steel/Welding | 2/10/2023 | Approved | VINCENT HANLEY |
| Deputy Steel/Welding | 2/14/2023 | Approved | VINCENT HANLEY |
| Deputy Steel/Welding | 2/16/2023 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2023 | Partial Approval | VINCENT HANLEY |
| Wood Frame | 3/10/2023 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2023 | Partial Approval | VINCENT HANLEY |
| Wood Frame | 5/8/2023 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2023 | Partial Approval | VINCENT HANLEY |
| Wood Frame | 6/5/2023 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 8/17/2023 | Approved | MORRIS JACKSON |
| ELECTRICAL-Rough | 8/18/2023 | Approved | JOHN KIDWELL |
| HVAC-Rough | 8/18/2023 | Corrections Issued | JOHN KIDWELL |
| HVAC-Rough | 8/31/2023 | Approved | VINCENT HANLEY |
| Sewer | 9/15/2023 | Partial Approval | VINCENT HANLEY |
| Service/Power Release | 9/18/2023 | Approved | VINCENT HANLEY |
| Service/Power Release | 9/19/2023 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2023 | Partial Approval | VINCENT HANLEY |
| Interior/Exterior Lathing | 10/19/2023 | Not Ready for Inspection | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2023 | Partial Approval | VINCENT HANLEY |
| Insulation | 11/13/2023 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 12/7/2023 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 12/7/2023 | Approved | VINCENT HANLEY |
| Insulation | 12/7/2023 | Partial Approval | VINCENT HANLEY |
| Interior/Exterior Lathing | 12/7/2023 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 12/26/2023 | Approved | VINCENT HANLEY |
| Green Building Final | 12/26/2023 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 12/26/2023 | Approved | VINCENT HANLEY |
| MERV13>=Rough | 12/26/2023 | Approved | VINCENT HANLEY |
| Shower Pan | 12/26/2023 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 12/26/2023 | Approved | VINCENT HANLEY |
| Drywall Nailing | 12/29/2023 | Approved | VINCENT HANLEY |
| Wood Frame | 1/11/2024 | Approved | VINCENT HANLEY |
| Pre-Inspection | 3/28/2024 | Approved | VINCENT HANLEY |
| Service/Power Release | 4/19/2024 | Approved | VINCENT HANLEY |
| Sewer | 5/20/2024 | Approved | JEFFREY BULL |
| Gas Test | 6/5/2024 | Approved | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 6/5/2024 | SGSOV Approved | MORRIS JACKSON |
| HVAC-Final | 6/14/2024 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 8/2/2024 | Partial Approval | THOMAS FINNILA |
| Gas Test | 8/2/2024 | Approved | THOMAS FINNILA |
| PLUMBING-Final | 8/2/2024 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Final | 8/30/2024 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 8/30/2024 | Approved | ALEXANDER HANDY |
| Final | 10/18/2024 | Corrections Issued | THOMAS FINNILA |
| MERV13>=Final | 10/18/2024 | Approved | THOMAS FINNILA |
| Smoke Detectors | 10/18/2024 | Approved | THOMAS FINNILA |
| Final | 10/24/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Final | 1/14/2025 | Corrections Issued | THOMAS FINNILA |
| Final | 2/18/2025 | OK to Issue CofO | THOMAS FINNILA |