2282 W 27TH ST 90018

Certificate Information: 2282 W 27TH ST 90018

Application / Permit
21014-10000-06478
Plan Check / Job No.
B21LA24351
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED NEW DETACHED ADU ADU CHECKED PER LAMC 12.22 A.33 (C)-(D)
Permit Issued
Issued on 8/23/2023
Issuing Office
Metro
Current Status
CofO Issued on 3/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/29/2021 APPLICANT
Assigned to Plan Check Engineer 1/27/2022 SUNMIN LEE
Corrections Issued 1/31/2022 SUNMIN LEE
Quality Review Completed 2/9/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 2/11/2022 APPLICANT
Applicant returned to address corrections 6/26/2023 SUNMIN LEE
Applicant returned to address corrections 6/27/2023 SUNMIN LEE
Applicant returned to address corrections 7/3/2023 SUNMIN LEE
Applicant returned to address corrections 7/21/2023 SUNMIN LEE
Plan Check Approved 8/23/2023 SUNMIN LEE
Issued 8/23/2023 APPLICANT
CofO in Progress 3/13/2025 SABAS ALONSO
Permit Finaled 3/13/2025 DEROLD HAUFF
CofO Issued 3/13/2025 DEROLD HAUFF
Permit Finaled 3/13/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/12/2022 ABEL CASILLAS
Eng Process Fee Ord 176,300 Cleared 4/19/2022 ABEL CASILLAS
Sewer availability Cleared 4/19/2022 ABEL CASILLAS
Low Impact Development Cleared 10/25/2022 LONDY ALVARADO
Roof/Waste drainage to street Cleared 11/8/2022 CELINA MORENO
HPOZ Cleared 5/17/2023 DANIEL MATA

Contact Information

Contractor Owner-Builder       ,
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592
Engineer Tagudar,, Fred; Lic. No.: C33612 255 W 5TH ST APT 706      SAN PEDRO, CA 90731
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803
Geologist Kaligi,, Adam Azad; Lic. No.: GEO9287 19197 GOLDEN VALLEY RD #709      SANTA CLARITA, CA 91387

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Subgrade 9/26/2023 Corrections Issued SABAS ALONSO
PLUMBING-Rough 9/26/2023 Conditional Approval SABAS ALONSO
Pre-Inspection 9/26/2023 Partial Inspection SABAS ALONSO
METHANE-Subgrade 9/28/2023 Approved SABAS ALONSO
Footing/Foundation/Slab 10/4/2023 Partial Approval SABAS ALONSO
Underground Mechanical 10/4/2023 Partial Approval SABAS ALONSO
Underground Mechanical 10/6/2023 Partial Approval SABAS ALONSO
Deputy Reinf. Concrete 10/11/2023 Conditional Approval SABAS ALONSO
Deputy Reinf. Concrete 10/13/2023 Conditional Approval SABAS ALONSO
Excavation/Setback/Form/Re-Bar 10/13/2023 Approved SABAS ALONSO
METHANE-Barrier 10/13/2023 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 12/12/2023 Corrections Issued SABAS ALONSO
Deputy Wood Construction 12/13/2023 Conditional Approval SABAS ALONSO
Pre-Inspection 4/16/2024 Partial Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 4/18/2024 Partial Approval SABAS ALONSO
Gas Test 4/25/2024 Not Ready for Inspection SABAS ALONSO
Underground Mechanical 4/25/2024 Partial Approval SABAS ALONSO
Sewer 5/1/2024 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 5/3/2024 Corrections Issued SABAS ALONSO
PLUMBING-Rough 5/3/2024 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 5/7/2024 Approved SABAS ALONSO
Sewer 5/7/2024 Approved SABAS ALONSO
PLUMBING-Rough 5/17/2024 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 5/21/2024 Approved SABAS ALONSO
ELECTRICAL-Rough 5/21/2024 Approved SABAS ALONSO
Green Building Rough 5/21/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 5/21/2024 Partial Approval SABAS ALONSO
METHANE-Rough 5/21/2024 Approved SABAS ALONSO
PLUMBING-Rough 5/21/2024 Approved SABAS ALONSO
Insulation 6/3/2024 Conditional Approval JOSH MEISTER
Gas Test 6/11/2024 Not Ready for Inspection SABAS ALONSO
Insulation 6/14/2024 Approved SABAS ALONSO
Drywall Nailing 6/21/2024 Approved SABAS ALONSO
Shower Pan 7/1/2024 Partial Approval SABAS ALONSO
Interior/Exterior Lathing 7/24/2024 Approved SABAS ALONSO
Pre-Inspection 9/30/2024 Partial Inspection SABAS ALONSO
ELECTRICAL-Final 11/4/2024 Corrections Issued SABAS ALONSO
ELECTRICAL-Final 11/8/2024 Approved SABAS ALONSO
Final 11/8/2024 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 11/8/2024 Approved SABAS ALONSO
Green Building Final 11/8/2024 Approved SABAS ALONSO
HVAC-Final 11/8/2024 Approved SABAS ALONSO
PLUMBING-Final 11/8/2024 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 11/8/2024 SGSOV Approved SABAS ALONSO
Smoke Detectors 11/8/2024 Approved SABAS ALONSO
Service/Power Release 11/12/2024 Corrections Issued SABAS ALONSO
Service/Power Release 11/15/2024 Approved SABAS ALONSO
Pre-Inspection 2/27/2025 Partial Inspection SABAS ALONSO
Final 3/12/2025 OK to Issue CofO SABAS ALONSO