6357 W 85TH ST 90045

Certificate Information: 6357 W 85TH ST 90045

Application / Permit
21014-10000-06475
Plan Check / Job No.
B21LA24334
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REAR SINGLE-STORY ADDITION AND REMODEL TO (E) SFD. SEE COMMENT.
Permit Issued
Issued on 4/27/2022
Issuing Office
Current Status
CofO Issued on 11/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/29/2021 APPLICANT
Assigned to Plan Check Engineer 1/7/2022 TSE MING HUANG
Corrections Issued 1/8/2022 TSE MING HUANG
Applicant returned to address corrections 3/30/2022 TSE MING HUANG
Plan Check Approved 4/27/2022 JOSEPH RAFOLS
Issued 4/27/2022 APPLICANT
Building Plans Picked Up 4/28/2022 APPLICANT
CofO in Progress 11/22/2022 HERBERT GIRON
Permit Finaled 11/30/2022 DANIEL ORRANTE
CofO Issued 11/30/2022 DANIEL ORRANTE
Permit Finaled 11/30/2022 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/27/2022 STEVE MELGAR
Sewer availability Cleared 1/27/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 3/8/2022 CINDY QI
Construction near power lines Cleared 3/21/2022 RIDWAN HARDY

Contact Information

Contractor Forsyth Construction Inc; Lic. No.: 560243-B 578 WASHINGTON BLVD #377      MARINA DEL REY, CA 90292
Engineer Erdelyi,, Peter Tibor; Lic. No.: C26962 2999 OVERLAND AVE STE 103      LOS ANGELES, CA 90064

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/4/2022 Conditional Approval JESUS RODRIGUEZ
Deputy Drilled-In Anchors 5/5/2022 Conditional Approval JESUS RODRIGUEZ
PLUMBING-Rough 5/9/2022 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 5/13/2022 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 6/13/2022 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 6/17/2022 Partial Approval RICHARD STEINBACH
BUILDING-Rough-Frame 6/27/2022 Conditional Approval JESUS RODRIGUEZ
ELECTRICAL-Rough 6/27/2022 Approved JESUS RODRIGUEZ
Green Building Rough 6/27/2022 Approved JESUS RODRIGUEZ
HVAC-Rough 6/27/2022 Corrections Issued JESUS RODRIGUEZ
Interior/Exterior Lathing 6/27/2022 Approved JESUS RODRIGUEZ
PLUMBING-Rough 6/27/2022 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 7/25/2022 Approved HERBERT GIRON
Insulation 7/25/2022 Approved HERBERT GIRON
Verify Sprinkler Sign Off 7/25/2022 Approved HERBERT GIRON
Drywall Nailing 8/3/2022 Approved HERBERT GIRON
ELECTRICAL-Final 11/8/2022 Corrections Issued HERBERT GIRON
Final 11/8/2022 Corrections Issued HERBERT GIRON
Green Building Final 11/8/2022 Not Ready for Inspection HERBERT GIRON
PLUMBING-Final 11/8/2022 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 11/8/2022 SGSOV Approved HERBERT GIRON
Smoke Detectors 11/8/2022 Approved HERBERT GIRON
ELECTRICAL-Final 11/17/2022 Corrections Issued HERBERT GIRON
Final 11/17/2022 Corrections Issued HERBERT GIRON
Gas Test 11/17/2022 Approved HERBERT GIRON
Green Building Final 11/17/2022 Approved HERBERT GIRON
HVAC-Final 11/17/2022 Corrections Issued HERBERT GIRON
PLUMBING-Final 11/17/2022 Approved HERBERT GIRON
ELECTRICAL-Final 11/21/2022 Approved HERBERT GIRON
Final 11/21/2022 OK to Issue CofO HERBERT GIRON
HVAC-Final 11/21/2022 Approved HERBERT GIRON