6357 W 85TH ST 90045
Certificate Information: 6357 W 85TH ST 90045
- Application / Permit
- 21014-10000-06475
- Plan Check / Job No.
- B21LA24334
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REAR SINGLE-STORY ADDITION AND REMODEL TO (E) SFD. SEE COMMENT.
- Permit Issued
- Issued on 4/27/2022
- Issuing Office
- Current Status
- CofO Issued on 11/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2022 | TSE MING HUANG |
| Corrections Issued | 1/8/2022 | TSE MING HUANG |
| Applicant returned to address corrections | 3/30/2022 | TSE MING HUANG |
| Plan Check Approved | 4/27/2022 | JOSEPH RAFOLS |
| Issued | 4/27/2022 | APPLICANT |
| Building Plans Picked Up | 4/28/2022 | APPLICANT |
| CofO in Progress | 11/22/2022 | HERBERT GIRON |
| Permit Finaled | 11/30/2022 | DANIEL ORRANTE |
| CofO Issued | 11/30/2022 | DANIEL ORRANTE |
| Permit Finaled | 11/30/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/27/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 1/27/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 3/8/2022 | CINDY QI |
| Construction near power lines | Cleared | 3/21/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Forsyth Construction Inc; Lic. No.: 560243-B | 578 WASHINGTON BLVD #377 MARINA DEL REY, CA 90292 |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 2999 OVERLAND AVE STE 103 LOS ANGELES, CA 90064 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/4/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Deputy Drilled-In Anchors | 5/5/2022 | Conditional Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 5/9/2022 | Partial Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 5/13/2022 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2022 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2022 | Partial Approval | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 6/27/2022 | Conditional Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 6/27/2022 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 6/27/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 6/27/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 6/27/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 6/27/2022 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 7/25/2022 | Approved | HERBERT GIRON |
| Insulation | 7/25/2022 | Approved | HERBERT GIRON |
| Verify Sprinkler Sign Off | 7/25/2022 | Approved | HERBERT GIRON |
| Drywall Nailing | 8/3/2022 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 11/8/2022 | Corrections Issued | HERBERT GIRON |
| Final | 11/8/2022 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 11/8/2022 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Final | 11/8/2022 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 11/8/2022 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 11/8/2022 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 11/17/2022 | Corrections Issued | HERBERT GIRON |
| Final | 11/17/2022 | Corrections Issued | HERBERT GIRON |
| Gas Test | 11/17/2022 | Approved | HERBERT GIRON |
| Green Building Final | 11/17/2022 | Approved | HERBERT GIRON |
| HVAC-Final | 11/17/2022 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 11/17/2022 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 11/21/2022 | Approved | HERBERT GIRON |
| Final | 11/21/2022 | OK to Issue CofO | HERBERT GIRON |
| HVAC-Final | 11/21/2022 | Approved | HERBERT GIRON |