208 1/2 W 84TH ST 90003

Certificate Information: 208 1/2 W 84TH ST 90003

Application / Permit
21014-10000-06474
Plan Check / Job No.
B21LA24333
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
GROUND AND SECOND FLOOR ADDITION TO AN (E) TWO-CAR GARAGE FOR AN ADU PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 11/8/2022
Issuing Office
Metro
Current Status
CofO Issued on 6/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/31/2021 APPLICANT
Assigned to Plan Check Engineer 1/27/2022 KHEDER ALRAZAA
Corrections Issued 1/30/2022 KHEDER ALRAZAA
Quality Review Completed 2/4/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 2/7/2022 APPLICANT
Applicant returned to address corrections 9/19/2022 KHEDER ALRAZAA
Plan Check Approved 11/8/2022 KHEDER ALRAZAA
Issued 11/8/2022 APPLICANT
CofO in Progress 6/6/2024 MICHAEL LEWIS
CofO Issued 6/6/2024 DEROLD HAUFF
Permit Finaled 6/6/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/15/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 2/22/2022 CELINA MORENO
Sewer availability Cleared 2/22/2022 CELINA MORENO
Low Impact Development Cleared 8/2/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 9/19/2022 JEREMY CHOK

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/9/2023 Partial Approval LILIANA PORTILLO
Sewer 2/9/2023 Approved LILIANA PORTILLO
Footing/Foundation/Slab 3/28/2023 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 5/16/2023 Partial Approval MICHAEL LEWIS
ELECTRICAL-Rough 9/12/2023 Corrections Issued MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 9/12/2023 Approved MICHAEL LEWIS
PLUMBING-Rough 9/12/2023 Corrections Issued MICHAEL LEWIS
Underground Mechanical 9/12/2023 Approved MICHAEL LEWIS
ELECTRICAL-Rough 10/11/2023 Approved MICHAEL LEWIS
PLUMBING-Rough 10/11/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 10/20/2023 Corrections Issued MICHAEL LEWIS
Green Building Rough 10/20/2023 Corrections Issued MICHAEL LEWIS
Underground Mechanical 10/20/2023 Approved MICHAEL LEWIS
HVAC-Rough 11/21/2023 Corrections Issued MICHAEL LEWIS
Interior/Exterior Lathing 11/21/2023 Approved MICHAEL LEWIS
Wood Frame 11/21/2023 Partial Inspection MICHAEL LEWIS
BUILDING-Rough-Frame 12/5/2023 Approved MICHAEL LEWIS
Green Building Rough 12/5/2023 Approved MICHAEL LEWIS
HVAC-Rough 12/5/2023 Approved MICHAEL LEWIS
Insulation 1/19/2024 Corrections Issued DAVID FEILER
Drywall Nailing 2/1/2024 Approved MICHAEL LEWIS
Insulation 2/1/2024 Approved MICHAEL LEWIS
Interior/Exterior Lathing 2/1/2024 Approved MICHAEL LEWIS
Final 4/8/2024 Corrections Issued MICHAEL LEWIS
Green Building Final 4/8/2024 Corrections Issued MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 4/8/2024 SGSOV Not Ready MICHAEL LEWIS
Smoke Detectors 4/8/2024 Approved MICHAEL LEWIS
Final 5/23/2024 Partial Inspection MICHAEL LEWIS
Green Building Final 5/23/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 5/23/2024 SGSOV Approved MICHAEL LEWIS
Final 5/31/2024 OK to Issue CofO MICHAEL LEWIS
Service/Power Release 6/3/2024 Approved MICHAEL LEWIS