4363 1/2 N EAGLE ROCK BLVD 90041

Certificate Information: 4363 1/2 N EAGLE ROCK BLVD 90041

Application / Permit
21014-10000-06472
Plan Check / Job No.
B21LA24329
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* CONVERT (E) DETACHED 1-CAR GARAGE TO ADU AND GROUND FLOOR ADDITION (795.05 SF) TO ADU PER LAMC 12.22.A.33(c)-(d). 2 BEDROOM 2 BATH
Permit Issued
Issued on 7/15/2022
Issuing Office
Current Status
CofO Issued on 11/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/5/2022 APPLICANT
Assigned to Plan Check Engineer 1/6/2022 VIVIAN LAO
Corrections Issued 1/7/2022 VIVIAN LAO
Applicant returned to address corrections 6/3/2022 VIVIAN LAO
Plan Check Approved 6/29/2022 VIVIAN LAO
Issued 7/15/2022 APPLICANT
CofO in Progress 11/14/2023 HAMIK HARTOUNIAN
CofO Issued 11/17/2023 DEROLD HAUFF
Permit Finaled 11/17/2023 DEROLD HAUFF

Permit Application Clearance Information

"Q" conditions Cleared 3/8/2022 ANACANY HURTADO
Grading Pre-Inspection Cleared 3/8/2022 LANNY MERRICK
Address approval Cleared 4/27/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 4/28/2022 JEANIE LAM
Sewer availability Cleared 4/28/2022 JEANIE LAM
Supp. Use District POD/CDO/TDO Cleared 4/28/2022 NASHYA JENSEN
Low Impact Development Cleared 5/17/2022 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 5/24/2022 STEVE MELGAR
GPI Written Notices Cleared 6/29/2022 VIVIAN LAO

Contact Information

Contractor Don Construction; Lic. No.: 840108-B 28063 MEMORY LN      VALENCIA, CA 91354
Engineer Hwang,, Junho; Lic. No.: S5592 815 FAIRVIEW AVE #205      SOUTH PASADENA, CA 91030

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/9/2022 Partial Inspection HAMIK HARTOUNIAN
Pre-Inspection 2/7/2023 Partial Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 3/3/2023 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 3/3/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 3/8/2023 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 3/8/2023 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 3/20/2023 Corrections Issued HAMIK HARTOUNIAN
Wood Frame 3/20/2023 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 4/4/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 4/4/2023 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 4/4/2023 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 4/7/2023 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 4/25/2023 Conditional Approval SCOTT FINNILA
ELECTRICAL-Rough 4/25/2023 Approved SCOTT FINNILA
Green Building Rough 4/25/2023 Approved SCOTT FINNILA
HVAC-Rough 4/25/2023 Approved SCOTT FINNILA
Interior/Exterior Lathing 4/25/2023 Not Ready for Inspection SCOTT FINNILA
PLUMBING-Rough 4/25/2023 Approved SCOTT FINNILA
Wood Frame 4/25/2023 Approved SCOTT FINNILA
BUILDING-Rough-Frame 5/1/2023 Approved SCOTT FINNILA
Insulation 5/1/2023 Conditional Approval SCOTT FINNILA
Interior/Exterior Lathing 5/1/2023 Partial Inspection SCOTT FINNILA
Sewer 5/1/2023 Approved SCOTT FINNILA
Shower Pan 5/1/2023 Approved SCOTT FINNILA
Underground Mechanical 5/1/2023 Partial Approval SCOTT FINNILA
Drywall Nailing 5/5/2023 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 5/5/2023 Partial Approval KATHRYN BUTTERWORTH
ELECTRICAL-Final 6/12/2023 Corrections Issued JEFFREY MEAD
Final 10/26/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Final 10/26/2023 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 10/26/2023 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 10/26/2023 Approved HAMIK HARTOUNIAN
Final 11/14/2023 OK to Issue CofO HAMIK HARTOUNIAN
Green Building Final 11/14/2023 Approved HAMIK HARTOUNIAN