4631 N TOBIAS AVE 91403
Certificate Information: 4631 N TOBIAS AVE 91403
- Application / Permit
- 21014-10000-06468
- Plan Check / Job No.
- B21LA24310
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Two-story, ground floor addition to (E) one-story Single Family Dwelling. Building to be sprinklered with NFPA 13D.
- Permit Issued
- Issued on 3/16/2022
- Issuing Office
- Current Status
- CofO Issued on 9/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/10/2022 | MINA HABILI |
| Corrections Issued | 1/11/2022 | MINA HABILI |
| Plan Check Approved | 3/8/2022 | STANLEY RAAP |
| Issued | 3/16/2022 | APPLICANT |
| Building Plans Picked Up | 3/23/2022 | APPLICANT |
| CofO in Progress | 8/1/2023 | MISAEL ESPARZA |
| Permit Finaled | 9/6/2023 | RUBEN SALAS |
| CofO Issued | 9/6/2023 | RUBEN SALAS |
| Permit Finaled | 9/6/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/21/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/24/2022 | CARLOS AGUILERA |
| ZI | Cleared | 2/4/2022 | MAXFIELD VERMY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Phillips,, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/24/2022 | Conditional Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 8/25/2022 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 9/6/2022 | Partial Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 9/6/2022 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2022 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2022 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 12/1/2022 | Corrections Issued | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 12/7/2022 | Conditional Approval | MISAEL ESPARZA |
| Deputy Wood Construction | 12/7/2022 | Conditional Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 1/18/2023 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2023 | Partial Approval | MISAEL ESPARZA |
| HVAC-Rough | 1/18/2023 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 1/18/2023 | Partial Approval | MISAEL ESPARZA |
| ELECTRICAL-Rough | 1/20/2023 | Approved | MISAEL ESPARZA |
| Green Building Rough | 1/20/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| MERV13>=Rough | 1/20/2023 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 1/20/2023 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 2/21/2023 | Conditional Approval | MISAEL ESPARZA |
| Green Building Rough | 2/21/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 2/21/2023 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 3/1/2023 | Approved | MISAEL ESPARZA |
| Green Building Rough | 3/1/2023 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 3/1/2023 | Approved | MISAEL ESPARZA |
| Insulation | 3/15/2023 | Partial Approval | MISAEL ESPARZA |
| Interior/Exterior Lathing | 3/15/2023 | Partial Approval | MISAEL ESPARZA |
| Shower Pan | 3/15/2023 | Partial Approval | MISAEL ESPARZA |
| Shower Pan | 3/22/2023 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 3/30/2023 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 3/30/2023 | Approved | MISAEL ESPARZA |
| Service/Power Release | 7/14/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Final | 7/19/2023 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 7/19/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| MERV13>=Final | 7/19/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 7/19/2023 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 7/19/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 7/19/2023 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Final | 7/27/2023 | Approved | MISAEL ESPARZA |
| HVAC-Final | 7/27/2023 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 7/27/2023 | Approved | MISAEL ESPARZA |
| Service/Power Release | 7/27/2023 | Approved | MISAEL ESPARZA |
| Final | 7/31/2023 | OK to Issue CofO | MISAEL ESPARZA |
| Green Building Final | 7/31/2023 | Approved | MISAEL ESPARZA |
| HVAC-Final | 7/31/2023 | Approved | MISAEL ESPARZA |
| MERV13>=Final | 7/31/2023 | Approved | MISAEL ESPARZA |
| Smoke Detectors | 7/31/2023 | Approved | MISAEL ESPARZA |