451 N NORMANDIE PL #8 90004

Certificate Information: 451 N NORMANDIE PL #8 90004

Application / Permit
21014-10000-06467
Plan Check / Job No.
B21LA24305
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
50 SF ADDITION AND COVERT EXISTING GARAGE TO ADU (259 SF) PER 12.22 A33 C&E TO EXISTING 2 STORY APARTMENT WITH CARPORT & GARAGE
Permit Issued
Issued on 4/14/2022
Issuing Office
Current Status
CofO Issued on 6/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2021 APPLICANT
Assigned to Plan Check Engineer 1/6/2022 STARR CHEN
Corrections Issued 1/8/2022 STARR CHEN
Quality Review Completed 1/11/2022 EUGENE BARBEAU
Applicant returned to address corrections 2/23/2022 STARR CHEN
Plan Check Approved 4/7/2022 STARR CHEN
Issued 4/14/2022 APPLICANT
Building Plans Picked Up 4/18/2022 APPLICANT
CofO in Progress 6/5/2023 TIMOTHY POWELL
CofO Issued 6/7/2023 ERNESTO CORRAL
Permit Finaled 6/7/2023 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 3/3/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 3/7/2022 AMAAN MALIK
Sewer availability Cleared 3/7/2022 AMAAN MALIK
Green Code Cleared 3/23/2022 STARR CHEN
DAS Clearance Cleared 3/24/2022 STARR CHEN

Contact Information

Contractor R L G Construction; Lic. No.: 1023091-B 5730 LA MIRADA AVENUE      LOS ANGELES, CA 90038
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/19/2022 Conditional Approval JONATHAN QUACH
Excavation/Setback/Form/Re-Bar 5/19/2022 Not Ready for Inspection JONATHAN QUACH
Footing/Foundation/Slab 5/23/2022 Partial Approval JONATHAN QUACH
Floor/Roof Diaphrgm/Shear Wall 6/3/2022 Not Ready for Inspection JONATHAN QUACH
Floor/Roof Diaphrgm/Shear Wall 6/28/2022 Partial Approval BRUCE CAMPBELL
Interior/Exterior Lathing 7/1/2022 Not Ready for Inspection DARRYL ARNOLD
Footing/Foundation/Slab 8/1/2022 Approved BRUCE CAMPBELL
Insulation 8/17/2022 Corrections Issued RAFAEL ESPINOZA
Insulation 8/22/2022 Approved BRUCE CAMPBELL
Drywall Nailing 9/2/2022 Approved RUSSELL BONVOULOIR
Floor/Roof Diaphrgm/Shear Wall 9/23/2022 Approved GREGORY POMISH
Final 1/23/2023 Partial Inspection RONALD JIMENEZ
Green Building Final 1/23/2023 Approved RONALD JIMENEZ
Green Building Rough 1/23/2023 Approved RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 1/23/2023 SGSOV Approved RONALD JIMENEZ
Smoke Detectors 1/23/2023 Approved RONALD JIMENEZ
Wood Frame 1/23/2023 Approved RONALD JIMENEZ
Final 5/4/2023 Not Ready for Inspection TIMOTHY POWELL
Final 6/5/2023 OK to Issue CofO TIMOTHY POWELL