4892 N WIOTA ST 90041
Certificate Information: 4892 N WIOTA ST 90041
- Application / Permit
- 21014-10000-06461
- Plan Check / Job No.
- B21LA24276
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- IRREGULAR ADDITION TO REAR OF EXISTING SINGLE FAMILY DWELLING AND INTERIOR KITCHEN REMODEL
- Permit Issued
- Issued on 3/23/2022
- Issuing Office
- Current Status
- CofO Issued on 3/30/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2022 | GEORGE ALVAREZ |
| Corrections Issued | 1/19/2022 | GEORGE ALVAREZ |
| Building Plans Picked Up | 1/24/2022 | APPLICANT |
| Plan Check Approved | 3/19/2022 | FERNANDO FLORES |
| Issued | 3/23/2022 | APPLICANT |
| CofO in Progress | 3/23/2023 | ALIZAH MAYAGOITIA |
| Permit Finaled | 3/30/2023 | DEROLD HAUFF |
| CofO Issued | 3/30/2023 | DEROLD HAUFF |
| Permit Finaled | 3/30/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/26/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2022 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 2/23/2022 | VASIL MIHALEV |
Contact Information
| Contractor | Gossett Construction Inc; Lic. No.: 880012-B | 15800 BEAVER RUN RD SANTA CLARITA, CA 91387 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/22/2022 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2022 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 7/1/2022 | Not Ready for Inspection | SCOTT FINNILA |
| MERV13>=Rough | 7/1/2022 | Not Ready for Inspection | SCOTT FINNILA |
| BUILDING-Rough-Frame | 8/19/2022 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 8/19/2022 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 8/19/2022 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 8/19/2022 | Partial Approval | CRAIG VAUGHAN |
| MERV13>=Rough | 8/19/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 8/19/2022 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 9/19/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 9/19/2022 | Partial Approval | CRAIG VAUGHAN |
| Drywall Nailing | 11/10/2022 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 3/22/2023 | Approved | ALIZAH MAYAGOITIA |
| Final | 3/22/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Final | 3/22/2023 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 3/22/2023 | Approved | ALIZAH MAYAGOITIA |
| MERV13>=Final | 3/22/2023 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 3/22/2023 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 3/22/2023 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 3/22/2023 | Approved | ALIZAH MAYAGOITIA |
| Final | 3/23/2023 | OK to Issue CofO | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 3/23/2023 | SGSOV Approved | ALIZAH MAYAGOITIA |