2027 N LAUGHLIN PARK DR 90027
Certificate Information: 2027 N LAUGHLIN PARK DR 90027
- Application / Permit
- 21014-10000-06459
- Plan Check / Job No.
- B21LA24267
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR and exterior ALTERATION AND ADDITION TO (E) 2-STORY SFD IN BHO AREA. (Not a major remodel Replacement cost 39% < 50%) 1 OF 3 Plan Check per 12.21.C 10 (Exempt per LAMC 12.21 C 10 (L)(2) . No addition after 2010
- Permit Issued
- Issued on 5/11/2022
- Issuing Office
- Current Status
- CofO Issued on 4/3/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2022 | SUNMIN LEE |
| Corrections Issued | 1/12/2022 | SUNMIN LEE |
| Quality Review Completed | 1/21/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 4/15/2022 | SUNMIN LEE |
| Building Plans Picked Up | 5/2/2022 | APPLICANT |
| Plan Check Approved | 5/5/2022 | SUNMIN LEE |
| Issued | 5/11/2022 | APPLICANT |
| CofO in Progress | 4/2/2026 | CRAIG VAUGHAN |
| Permit Finaled | 4/3/2026 | DEROLD HAUFF |
| CofO Issued | 4/3/2026 | DEROLD HAUFF |
| Permit Finaled | 4/3/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Private street | Cleared | 3/25/2022 | DALIA MOKAYED |
| City Hist. Cultural Monument | Cleared | 3/29/2022 | MAX LODER |
| HPOZ | Cleared | 3/29/2022 | MAX LODER |
| Historic monument | Cleared | 3/29/2022 | MAX LODER |
| Sewer availability | Cleared | 3/29/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/30/2022 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 4/15/2022 | SUNMIN LEE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/9/2022 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 6/15/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 7/11/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| HVAC-Rough | 7/14/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 7/18/2023 | Approved | BRIAN SULLIVAN |
| Deputy Wood Construction | 8/2/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 8/4/2023 | Approved | JOAQUIN GREENOUGH |
| Underground Mechanical | 8/4/2023 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2023 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 9/11/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 9/29/2023 | Partial Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 10/26/2023 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 10/26/2023 | Approved | JOAQUIN GREENOUGH |
| Insulation | 3/13/2024 | Approved | ROY SPAULDING |
| Drywall Nailing | 5/22/2024 | Approved | BRIAN SULLIVAN |
| Shower Pan | 8/19/2024 | Approved | ROY SPAULDING |
| Service/Power Release | 10/25/2024 | Approved | CRAIG VAUGHAN |
| Final | 11/12/2025 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 11/12/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Final | 11/12/2025 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 11/12/2025 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 11/12/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 11/18/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 11/18/2025 | Approved | CRAIG VAUGHAN |
| Smoke Detectors | 11/18/2025 | Approved | CRAIG VAUGHAN |
| Final | 4/1/2026 | OK to Issue CofO | CRAIG VAUGHAN |