129 S WILTON DR 90004
Certificate Information: 129 S WILTON DR 90004
- Application / Permit
- 21014-10000-06457
- Plan Check / Job No.
- B21LA24253
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF EXISTING 2-CAR GARAGE TO ADU WITH ADDITION ADU PER STATE LAW CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g) 800 SQFT MAX ADU 16' MAX HEIGHT
- Permit Issued
- Issued on 6/20/2024
- Issuing Office
- Metro
- Current Status
- Issued on 6/20/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2022 | JAD BASMA |
| Corrections Issued | 2/4/2022 | JAD BASMA |
| Quality Review Completed | 2/9/2022 | KEN GILL |
| Applicant returned to address corrections | 2/22/2022 | JAD BASMA |
| Applicant returned to address corrections | 10/26/2022 | JAD BASMA |
| Applicant returned to address corrections | 12/16/2022 | JAD BASMA |
| Applicant returned to address corrections | 11/30/2023 | JAD BASMA |
| Plan Check Approved | 1/26/2024 | JAD BASMA |
| Issued | 6/20/2024 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 8/15/2023 | NEIL TUANO |
| Address approval | Cleared | 8/16/2023 | NEIL TUANO |
| Historic Resource Verification | Cleared | 8/21/2023 | MAX LODER |
| Low Impact Development | Cleared | 10/30/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 11/8/2023 | JEANIE LAM |
Contact Information
| Contractor | Build Zone Corp; Lic. No.: 1098273-B | 3925 GUARDIA AVENUE LOS ANGELES, CA 90032 |
| Engineer | Structural, Design Plus Inc; Lic. No.: C58024 | 15053 VENTURA BLVD 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/16/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Footing/Foundation/Slab | 9/16/2024 | Corrections Issued | JEFFREY MEAD |
| Footing/Foundation/Slab | 9/26/2024 | Partial Inspection | JEFFREY MEAD |
| Underground Mechanical | 10/10/2024 | Approved | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 10/24/2024 | Approved | JEFFREY MEAD |
| Wood Frame | 4/2/2025 | Corrections Issued | JEFFREY MEAD |
| ELECTRICAL-Rough | 4/8/2025 | Corrections Issued | JEFFREY MEAD |
| PLUMBING-Rough | 4/8/2025 | Approved | JEFFREY MEAD |
| ELECTRICAL-Rough | 6/24/2025 | Approved | WILLIAM SIERRA |
| Excavation/Setback/Form/Re-Bar | 8/13/2025 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 8/13/2025 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2025 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 9/12/2025 | Partial Approval | JEFFREY MEAD |
| BUILDING-Rough-Frame | 10/17/2025 | Corrections Issued | JEFFREY MEAD |
| HVAC-Rough | 10/17/2025 | Corrections Issued | JEFFREY MEAD |
| BUILDING-Rough-Frame | 10/21/2025 | Approved | JEFFREY MEAD |
| Green Building Rough | 10/21/2025 | Approved | JEFFREY MEAD |
| HVAC-Rough | 10/21/2025 | Approved | JEFFREY MEAD |
| ELECTRICAL-Rough | 10/23/2025 | Approved | JEFFREY MEAD |
| Insulation | 10/23/2025 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 10/23/2025 | Approved | JEFFREY MEAD |
| Drywall Nailing | 10/30/2025 | Approved | JEFFREY MEAD |
| Final | 3/26/2026 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Final | 3/26/2026 | Not Ready for Inspection | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 3/26/2026 | SGSOV Not Ready | JEFFREY MEAD |
| Smoke Detectors | 3/26/2026 | Not Ready for Inspection | JEFFREY MEAD |