1863 1/2 S REDONDO BLVD 90019

Certificate Information: 1863 1/2 S REDONDO BLVD 90019

Application / Permit
21014-10000-06387
Plan Check / Job No.
B21LA23940
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE (390 SF) INTO ADU W/ ADDITION OF 305 SF per ordinance
Permit Issued
Issued on 6/27/2022
Issuing Office
Metro
Current Status
CofO Issued on 3/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/26/2021 APPLICANT
Assigned to Plan Check Engineer 1/4/2022 JOSEPH RAFOLS
Corrections Issued 1/5/2022 JOSEPH RAFOLS
Building Plans Picked Up 1/5/2022 APPLICANT
Plan Check Approved 5/25/2022 MINA HABILI
Issued 6/27/2022 APPLICANT
CofO in Progress 3/7/2024 STUART CHAPMAN
CofO Issued 3/8/2024 DEROLD HAUFF
Permit Finaled 3/8/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/6/2022 JEANETTE VONG
Roof/Waste drainage to street Cleared 1/6/2022 JEANETTE VONG
Tenant Habitability Plan Cleared 3/9/2022 RICHARD BRINSON
Construction near power lines Cleared 3/15/2022 TINA MIRANDA
Eng Process Fee Ord 176,300 Cleared 4/28/2022 JEANETTE VONG
Sewer availability Cleared 4/28/2022 JEANETTE VONG

Contact Information

Contractor Bejarano'S Construction; Lic. No.: 711144-B 3258 OCOTILLO DR      LAUGHLIN, NV 89029
Engineer Gonzalez,, Felix Bolivar; Lic. No.: C64738 14619 CATALINA AVE      GARDENA, CA 90247

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/3/2022 Corrections Issued JOSE AVILA
Pre-Inspection 8/9/2022 Approved JOSE AVILA
Underground Mechanical 12/29/2022 Partial Approval JOSE AVILA
Footing/Foundation/Slab 1/24/2023 Corrections Issued MICHAEL LEWIS
Footing/Foundation/Slab 2/8/2023 Corrections Issued JOSE AVILA
Deputy Drilled-In Anchors 4/12/2023 Conditional Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 5/3/2023 Approved JOSE AVILA
PLUMBING-Rough 5/3/2023 Approved JOSE AVILA
BUILDING-Rough-Frame 5/10/2023 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 5/10/2023 Approved ALIZAH MAYAGOITIA
HVAC-Rough 5/10/2023 Approved ALIZAH MAYAGOITIA
Green Building Rough 5/19/2023 Approved STUART CHAPMAN
Insulation 5/19/2023 Approved STUART CHAPMAN
Interior/Exterior Lathing 5/19/2023 Partial Approval STUART CHAPMAN
Drywall Nailing 5/26/2023 Approved JOSE AVILA
Gas Test 10/18/2023 Partial Approval BRENDAN MORELLI
Sewer 10/18/2023 Corrections Issued BRENDAN MORELLI
Underground Mechanical 10/18/2023 Partial Approval BRENDAN MORELLI
ELECTRICAL-Final 11/15/2023 Corrections Issued LILIANA PORTILLO
Pre-Inspection 12/22/2023 Not Ready for Inspection RICHARD DOCKUS
ELECTRICAL-Final 1/10/2024 Corrections Issued RONNIE MINDANAO
Final 1/10/2024 Corrections Issued RONNIE MINDANAO
ELECTRICAL-Final 2/20/2024 Not Ready for Inspection STUART CHAPMAN
Final 2/20/2024 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 2/20/2024 Approved STUART CHAPMAN
Green Building Final 2/20/2024 Approved STUART CHAPMAN
HVAC-Final 2/20/2024 Approved STUART CHAPMAN
PLUMBING-Final 2/20/2024 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 2/20/2024 SGSOV Approved STUART CHAPMAN
Smoke Detectors 2/20/2024 Approved STUART CHAPMAN
ELECTRICAL-Final 2/29/2024 Approved STUART CHAPMAN
HVAC-Final 2/29/2024 Approved STUART CHAPMAN
PLUMBING-Final 2/29/2024 Approved STUART CHAPMAN
Service/Power Release 2/29/2024 Approved STUART CHAPMAN
Final 3/7/2024 OK to Issue CofO STUART CHAPMAN