2587 N GLENDOWER AVE 90027
Certificate Information: 2587 N GLENDOWER AVE 90027
- Application / Permit
- 21014-10000-06384
- Plan Check / Job No.
- B21LA23936
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ALTERATION TPO EXISTING SINGLE FAMILY RESIDENCE AND INTERIOR DESIGN. MAJOR REMODEL.
- Permit Issued
- Issued on 6/16/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 12/19/2023
Permit Application Status History
| Submitted | 1/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2022 | YOUNG KIM |
| Corrections Issued | 2/3/2022 | MICHAEL LOPEZ |
| Quality Review Completed | 2/7/2022 | SEAN DANG |
| Building Plans Picked Up | 2/10/2022 | APPLICANT |
| Applicant returned to address corrections | 5/18/2022 | MICHAEL LOPEZ |
| Plan Check Approved | 6/9/2022 | MICHAEL LOPEZ |
| Issued | 6/16/2022 | APPLICANT |
| Permit Finaled | 12/19/2023 | JEFFREY MEAD |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/2/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 3/4/2022 | AMAAN MALIK |
Contact Information
| Contractor | Rincon Builders Inc; Lic. No.: 988687-B | 19528 VENTURA BLVD #183 TARZANA, CA 91356 |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Steel/Welding | 10/18/2022 | Partial Approval | JOSEPH MCGARRY |
| Rough-Elec/Plmb/HVAC | 11/17/2022 | Partial Approval | JOSEPH MCGARRY |
| Wood Frame | 11/17/2022 | Partial Approval | JOSEPH MCGARRY |
| Wood Frame | 12/19/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 2/16/2023 | Not Ready for Inspection | RAUL BARAJAS |
| ELECTRICAL-Rough | 2/16/2023 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 2/16/2023 | Not Ready for Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 2/22/2023 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 2/22/2023 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 2/22/2023 | Partial Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 3/10/2023 | Partial Approval | JOSEPH MCGARRY |
| Shower Pan | 3/20/2023 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 3/29/2023 | Approved | JOSEPH MCGARRY |
| Wood Frame | 4/20/2023 | Approved | JOSEPH MCGARRY |
| Insulation | 4/25/2023 | Approved | JOSEPH MCGARRY |
| Deputy Steel/Welding | 5/3/2023 | Partial Approval | SCOTT FINNILA |
| Drywall Nailing | 5/4/2023 | Approved | LILIANA PORTILLO |
| Final | 11/9/2023 | Corrections Issued | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 11/9/2023 | SGSOV Approved | JOSEPH MCGARRY |
| Smoke Detectors | 11/9/2023 | Approved | JOSEPH MCGARRY |
| Final | 12/19/2023 | Permit Finaled | JEFFREY MEAD |