1287 1/4 S QUEEN ANNE PL 90019

Certificate Information: 1287 1/4 S QUEEN ANNE PL 90019

Application / Permit
21014-10000-06382
Plan Check / Job No.
B21LA23930
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(2) Duplex
Work Description
ePlan CONVERT (E) GARAGE TO ONE ADU PER GCS 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) AND (g) WITH (E) DWELLING AT SECOND STORY
Permit Issued
Issued on 5/17/2022
Issuing Office
Current Status
CofO Issued on 8/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2021 APPLICANT
Assigned to Plan Check Engineer 1/20/2022 CRYSTEL MAALOUF
Corrections Issued 1/30/2022 CRYSTEL MAALOUF
Quality Review Completed 2/3/2022 SAI KHUM
Plan Check Approved 4/28/2022 CRYSTEL MAALOUF
Issued 5/17/2022 APPLICANT
CofO in Progress 8/24/2023 ALFREDO LOPEZ
Permit Finaled 8/24/2023 ERNESTO CORRAL
CofO Issued 8/24/2023 ERNESTO CORRAL
Permit Finaled 8/24/2023 ERNESTO CORRAL

Permit Application Clearance Information

Tenant Habitability Plan Cleared 3/3/2022 MICHAEL SOTO
Address approval Cleared 4/18/2022 CINDY QI
Sewer availability Cleared 4/18/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 4/19/2022 CINDY QI

Contact Information

Contractor Titan Contracting Services Inc; Lic. No.: 976552-B 13434 RAYMER STREET      NORTH HOLLYWOOD, CA 91605
Engineer Ni,, Zhang Yuan; Lic. No.: C68149 743 S SIERRA VISTA AVE C      ALHAMBRA, CA 91801

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/21/2022 Not Ready for Inspection GREGORY POMISH
Footing/Foundation/Slab 12/2/2022 Conditional Approval RAFAEL ESPINOZA
METHANE-Barrier 12/2/2022 Approved RAFAEL ESPINOZA
METHANE-Subgrade 12/2/2022 Approved RAFAEL ESPINOZA
METHANE-Rough 1/4/2023 Approved ALFREDO LOPEZ
Wood Frame 1/4/2023 Conditional Approval ALFREDO LOPEZ
Insulation 1/6/2023 Approved ALFREDO LOPEZ
Drywall Nailing 1/12/2023 Partial Approval ALFREDO LOPEZ
Interior/Exterior Lathing 1/18/2023 Partial Approval JEROME BLACKWOOD
Final 7/7/2023 Not Ready for Inspection ALFREDO LOPEZ
Footing/Foundation/Slab 7/7/2023 Approved ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 7/7/2023 SGSOV Approved ALFREDO LOPEZ
Smoke Detectors 7/7/2023 Approved ALFREDO LOPEZ
Wood Frame 7/7/2023 Approved ALFREDO LOPEZ
Final 8/4/2023 Conditional Approval ALFREDO LOPEZ