3925 N COLLIS AVE 90032
Certificate Information: 3925 N COLLIS AVE 90032
- Application / Permit
- 21014-10000-06379
- Plan Check / Job No.
- B21LA23925
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE to A.D.U. CONVERSION WITH ADDITION
- Permit Issued
- Issued on 6/10/2022
- Issuing Office
- Metro
- Current Status
- Issued on 6/10/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2022 | CRYSTEL MAALOUF |
| Corrections Issued | 1/10/2022 | CRYSTEL MAALOUF |
| Quality Review Completed | 1/13/2022 | KEN GILL |
| Building Plans Picked Up | 1/18/2022 | APPLICANT |
| Applicant returned to address corrections | 2/8/2022 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 2/16/2022 | CRYSTEL MAALOUF |
| Plan Check Approved | 4/11/2022 | CRYSTEL MAALOUF |
| Issued | 6/10/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/20/2022 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 1/20/2022 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 1/20/2022 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 1/20/2022 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 1/20/2022 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 1/20/2022 | STEVE MELGAR |
| Street width determination | Cleared | 1/20/2022 | STEVE MELGAR |
| Grading Pre-Inspection | Cleared | 1/27/2022 | ROBERT HUGHES |
| Eng Process Fee Ord 176,300 | Cleared | 2/9/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 2/9/2022 | STEVE MELGAR |
| Low Impact Development | Cleared | 2/10/2022 | CHRIS VONG |
| "D" conditions | Cleared | 2/17/2022 | MAYELA VILLA |
| "Q" conditions | Cleared | 2/17/2022 | MAYELA VILLA |
| ZI | Cleared | 2/17/2022 | MAYELA VILLA |
| GPI Written Notices | Cleared | 2/24/2022 | CRYSTEL MAALOUF |
| Roof/Waste drainage to street | Cleared | 2/25/2022 | CHRISTOPHER ROCHA |
| Disturb/Remove Protected Trees | Cleared | 3/16/2022 | CRYSTEL MAALOUF |
| Hydrant and Access approval | Cleared | 3/16/2022 | CINDY JOSSELYN |
| Hold | Cleared | 8/17/2022 | PRISCILLA RUIZ |
Contact Information
| Contractor | Franco Pacific Builders; Lic. No.: 1035110-B | 1012 W BEVERLY BLVD #152 MONTEBELLO, CA 90640 |
| Engineer | Chan,, Albert F; Lic. No.: C61343 | 2261 PEPPERWOOD LN CORONA, CA 92882 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/19/2022 | Approved | AMY COLIN |
| Footing/Foundation/Slab | 8/23/2022 | Conditional Approval | AMY COLIN |
| PLUMBING-Rough | 8/23/2022 | Partial Approval | AMY COLIN |
| BUILDING-Rough-Frame | 9/22/2022 | Partial Inspection | SCOTT FINNILA |
| Green Building Rough | 9/22/2022 | Partial Inspection | SCOTT FINNILA |
| Wood Frame | 9/22/2022 | Partial Inspection | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 11/23/2022 | Partial Approval | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2022 | Partial Approval | RUBEN SALAS |
| ELECTRICAL-Rough | 1/11/2023 | Partial Approval | AMY COLIN |
| PLUMBING-Rough | 1/11/2023 | Corrections Issued | AMY COLIN |
| PLUMBING-Rough | 2/28/2023 | Partial Approval | AMY COLIN |
| Sewer | 2/28/2023 | Partial Approval | AMY COLIN |
| PLUMBING-Rough | 3/20/2023 | Not Ready for Inspection | AMY COLIN |
| PLUMBING-Rough | 3/29/2023 | Approved | AMY COLIN |
| Pre-Inspection | 4/27/2023 | Partial Inspection | RUBEN SALAS |
| Sewer | 6/8/2023 | Partial Approval | RUBEN SALAS |
| Gas Test | 8/16/2023 | Approved | AMY COLIN |
| Footing/Foundation/Slab | 8/28/2023 | Approved | AMY COLIN |
| Grounding or Bonding | 8/31/2023 | Partial Inspection | AMY COLIN |
| Wood Frame | 9/14/2023 | Partial Approval | AMY COLIN |
| Interior/Exterior Lathing | 10/23/2023 | Not Ready for Inspection | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2023 | Partial Approval | ROY SPAULDING |
| BUILDING-Rough-Frame | 1/29/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Rough | 1/29/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 1/29/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 2/13/2024 | Corrections Issued | RUBEN SALAS |
| ELECTRICAL-Rough | 3/22/2024 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2024 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 3/22/2024 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 3/22/2024 | Conditional Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 3/22/2024 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 3/29/2024 | Conditional Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 3/29/2024 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2024 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 3/29/2024 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 3/29/2024 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 3/29/2024 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 5/8/2024 | Corrections Issued | LILIANA PORTILLO |
| Insulation | 7/1/2024 | Corrections Issued | LILIANA PORTILLO |
| Insulation | 7/11/2024 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 9/11/2024 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 9/11/2024 | Approved | LILIANA PORTILLO |
| Green Building Rough | 9/11/2024 | Approved | LILIANA PORTILLO |
| Shower Pan | 9/24/2024 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 10/16/2024 | Approved | LILIANA PORTILLO |
| Final | 12/11/2024 | Corrections Issued | LILIANA PORTILLO |
| Service/Power Release | 12/11/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 12/31/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 1/7/2025 | Partial Approval | BRENDAN MORELLI |
| Special/Order Compliance | 1/7/2025 | Corrections Issued | BRENDAN MORELLI |
| Service/Power Release | 1/29/2025 | Approved | LILIANA PORTILLO |