Excavation/Setback/Form/Re-Bar
|
2/8/2023
|
Corrections Issued
|
MICHAEL PELHAM
|
|
Excavation/Setback/Form/Re-Bar
|
2/21/2023
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Special/Order Compliance
|
2/22/2023
|
Partial Approval
|
MICHAEL PELHAM
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/20/2023
|
Partial Approval
|
STEPHANIE SWANSON
|
|
Excavation/Setback/Form/Re-Bar
|
4/6/2023
|
Conditional Approval
|
CARLOS MATAMOROS
|
|
Footing/Foundation/Slab
|
4/17/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
4/26/2023
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
5/17/2023
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
5/24/2023
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
6/1/2023
|
Partial Approval
|
HERBERT GIRON
|
|
Excavation/Setback/Form/Re-Bar
|
6/5/2023
|
Conditional Approval
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
6/12/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Drilled-In Anchors
|
6/15/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
6/15/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
6/21/2023
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
6/23/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
6/29/2023
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
7/3/2023
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/12/2023
|
Conditional Approval
|
CARLOS MATAMOROS
|
|
Masonry Wall/Backfill
|
7/17/2023
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
PLUMBING-Rough
|
8/25/2023
|
Approved
|
CARLOS MATAMOROS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/31/2023
|
Approved
|
CARLOS MATAMOROS
|
|
HVAC-Rough
|
8/31/2023
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
ELECTRICAL-Rough
|
10/27/2023
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
HVAC-Rough
|
10/27/2023
|
Approved
|
CARLOS MATAMOROS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/9/2023
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
11/20/2023
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
ELECTRICAL-Rough
|
11/20/2023
|
Approved
|
CARLOS MATAMOROS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/20/2023
|
Approved
|
CARLOS MATAMOROS
|
|
Green Building Rough
|
11/20/2023
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
BUILDING-Rough-Frame
|
11/30/2023
|
Approved
|
BRENDAN LOONEY
|
|
Green Building Rough
|
11/30/2023
|
Approved
|
BRENDAN LOONEY
|
|
Interior/Exterior Lathing
|
11/30/2023
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
Verify Sprinkler Sign Off
|
11/30/2023
|
Approved
|
BRENDAN LOONEY
|
|
Insulation
|
12/7/2023
|
Approved
|
CARLOS MATAMOROS
|
|
Interior/Exterior Lathing
|
12/7/2023
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Interior/Exterior Lathing
|
12/13/2023
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Shower Pan
|
12/13/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Drywall Nailing
|
12/18/2023
|
Approved
|
CHRISTOPHER WILSON
|
|
Shower Pan
|
12/18/2023
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
12/20/2023
|
Approved
|
CARLOS MATAMOROS
|
|
Shower Pan
|
12/20/2023
|
Approved
|
CARLOS MATAMOROS
|
|
Interior/Exterior Lathing
|
3/7/2024
|
Approved
|
CARLOS MATAMOROS
|
|
Gas Test
|
4/10/2024
|
Approved
|
CARLOS MATAMOROS
|
|
PLUMBING-Final
|
4/10/2024
|
Approved
|
CARLOS MATAMOROS
|
|
ELECTRICAL-Final
|
4/17/2024
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
Final
|
4/17/2024
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Footing/Foundation/Slab
|
4/17/2024
|
Approved
|
CARLOS MATAMOROS
|
|
Green Building Final
|
4/17/2024
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
HVAC-Final
|
4/17/2024
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
SGSOV-Seismic Gas S/O Valve
|
4/17/2024
|
SGSOV Approved
|
CARLOS MATAMOROS
|
|
Smoke Detectors
|
4/17/2024
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
ELECTRICAL-Final
|
5/29/2024
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Green Building Final
|
5/29/2024
|
Approved
|
CARLOS MATAMOROS
|
|
HVAC-Final
|
5/29/2024
|
Approved
|
CARLOS MATAMOROS
|
|
Service/Power Release
|
6/6/2024
|
Approved
|
CARLOS MATAMOROS
|
|
Final
|
6/13/2024
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
Smoke Detectors
|
9/6/2024
|
Approved
|
CARLOS MATAMOROS
|
|
Final
|
3/28/2025
|
OK to Issue CofO
|
CARLOS MATAMOROS
|