1915 N CRESCENT HEIGHTS BLVD 90069

Certificate Information: 1915 N CRESCENT HEIGHTS BLVD 90069

Application / Permit
21014-10000-06338
Plan Check / Job No.
B21LA23699
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SECOND STORY ADDITION & BASEMENT ADDITION & INTERIOR AND EXTERIOR RENNOVATIONS TO & TRELLIS OVER GROUND FLOOR DECK TO (E) SFD W/ ATTACHED GARAGE. PROPOSED WORK IS LESS THAN 50% OF (E) REPLACEMENT VALUE. SEE COMMENTS
Permit Issued
Issued on 1/23/2024
Issuing Office
Metro
Current Status
Issued on 1/23/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/21/2021 APPLICANT
Assigned to Plan Check Engineer 1/20/2022 SERGIO GUTIERREZ
Corrections Issued 1/27/2022 SERGIO GUTIERREZ
Quality Review Completed 2/3/2022 FARUK SEZER
Building Plans Picked Up 2/7/2022 APPLICANT
Applicant returned to address corrections 2/23/2022 SERGIO GUTIERREZ
Applicant returned to address corrections 7/22/2022 SERGIO GUTIERREZ
Applicant returned to address corrections 2/10/2023 SERGIO GUTIERREZ
Applicant returned to address corrections 7/27/2023 SERGIO GUTIERREZ
Applicant returned to address corrections 8/4/2023 SERGIO GUTIERREZ
Plan Check Approved 1/18/2024 SERGIO GUTIERREZ
Issued 1/23/2024 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 2/14/2022 KHOUNG LE
BHO/Hillside ordinance Cleared 2/14/2022 KHOUNG LE
BHO/Hillside ordinance Cleared 2/14/2022 KHOUNG LE
BHO/Hillside ordinance Cleared 2/14/2022 KHOUNG LE
Eng Process Fee Ord 176,300 Cleared 2/16/2022 KHOUNG LE
Sewer availability Cleared 2/16/2022 KHOUNG LE
Hydrant and Access approval Cleared 4/11/2022 LAURINDA MEADE
ZA Case Cleared 4/15/2022 DANIEL CORONADO
Low Impact Development Cleared 9/11/2023 SHAHIN KHAZEY
Roof/Waste drainage to street Cleared 9/15/2023 KHOUNG LE
Work Adjacent to Public Way Cleared 1/8/2024 LARRY LEE
GPI Written Notices Cleared 1/18/2024 SERGIO GUTIERREZ
Grading Pre-Inspection Cleared 1/18/2024 SERGIO GUTIERREZ

Contact Information

Architect Obermeyer,, Andrew William; Lic. No.: C32269 2801 OCEAN PARK BLVD #242      SANTA MONICA, CA 90405
Contractor Norcio Construction Inc; Lic. No.: 1006731-B 1756 CLINTON STREET      LOS ANGELES, CA 90026
Engineer Benson,, William Randolph; Lic. No.: L4503 13535 WINGO ST      ARLETA, CA 91331
Engineer Varela, Olivas, Benjamin; Lic. No.: S5714 6007 WASHINGTON BLVD      CULVER CITY, CA 90232

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/1/2024 Partial Inspection RAUL BARAJAS
Deputy Reinf. Concrete 5/29/2024 Conditional Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 6/10/2024 Partial Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 7/2/2024 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 7/2/2024 Partial Approval RAUL BARAJAS
Grounding or Bonding 7/3/2024 Approved RAUL BARAJAS
Deputy Reinf. Concrete 7/8/2024 Conditional Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 7/25/2024 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 7/25/2024 Not Ready for Inspection RAUL BARAJAS
Footing/Foundation/Slab 7/31/2024 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 8/1/2024 Conditional Approval ANTHONY RAMOS
Footing/Foundation/Slab 9/20/2024 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 9/23/2024 Conditional Approval BRIAN SULLIVAN
Deputy Reinf. Concrete 10/2/2024 Conditional Approval BRIAN SULLIVAN
Piling/Pier/Caisson 10/2/2024 Partial Approval BRIAN SULLIVAN
Deputy Reinf. Concrete 10/3/2024 Conditional Approval BRIAN SULLIVAN
PLUMBING-Rough 10/17/2024 Partial Approval ALIZAH MAYAGOITIA
Sewer 10/17/2024 Partial Approval ALIZAH MAYAGOITIA
Deputy Steel/Welding 10/23/2024 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 10/30/2024 Approved RAUL BARAJAS
Structural Steel Frame 10/30/2024 Partial Approval RAUL BARAJAS
Deputy Steel/Welding 11/15/2024 Conditional Approval RAUL BARAJAS
Deputy Wood Construction 12/12/2024 Conditional Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 12/12/2024 Partial Approval CRAIG VAUGHAN
Deputy Drilled-In Anchors 3/19/2025 Conditional Approval BRENDAN MORELLI
Deputy Wood Construction 3/19/2025 Conditional Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 3/19/2025 Partial Approval ROY SPAULDING
Insulation 4/16/2025 Approved ROY SPAULDING
PLUMBING-Rough 4/17/2025 Approved CRAIG VAUGHAN
Deputy Wood Construction 4/30/2025 Partial Approval SCOTT FINNILA
HVAC-Rough 4/30/2025 Approved ROY SPAULDING
Shower Pan 5/9/2025 Approved ROY SPAULDING
BUILDING-Rough-Frame 5/15/2025 Not Ready for Inspection ROY SPAULDING
ELECTRICAL-Rough 5/15/2025 Approved ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 5/15/2025 Approved ROY SPAULDING
Green Building Rough 5/15/2025 Not Ready for Inspection ROY SPAULDING
BUILDING-Rough-Frame 6/13/2025 Corrections Issued BRENDAN MORELLI
Interior/Exterior Lathing 6/13/2025 Partial Approval BRENDAN MORELLI
Insulation 6/24/2025 Corrections Issued BRENDAN MORELLI
Interior/Exterior Lathing 6/24/2025 Not Ready for Inspection BRENDAN MORELLI
BUILDING-Rough-Frame 6/26/2025 Approved BRENDAN MORELLI
Green Building Rough 6/26/2025 Approved BRENDAN MORELLI
Insulation 6/26/2025 Approved BRENDAN MORELLI
Interior/Exterior Lathing 6/26/2025 Partial Approval BRENDAN MORELLI
Drywall Nailing 7/28/2025 Approved ROY SPAULDING
Interior/Exterior Lathing 8/13/2025 Approved ROY SPAULDING
ELECTRICAL-Final 6/15/2026 Not Ready for Inspection ROY SPAULDING
Service/Power Release 6/15/2026 Corrections Issued ROY SPAULDING