17-19 E LIGHTHOUSE ST 90292

Certificate Information: 17-19 E LIGHTHOUSE ST 90292

Application / Permit
21014-10000-06296
Plan Check / Job No.
B21LA23583
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
MINOR RECONFIGURATION OF INTERIOR FLOOR PLAN AND SOUTH FACADE OF (E) 3-STORY DUPLEX. NO CHANGES TO (E) HEIGHT, DENSITY OR INTENSITY OF USE. INFILL PORTION OF THE THIRD FLOOR TO CREATE 3RD BEDROOM.
Permit Issued
Issued on 6/23/2022
Issuing Office
Metro
Current Status
CofO Issued on 1/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/25/2021 APPLICANT
Assigned to Plan Check Engineer 1/20/2022 KHEDER ALRAZAA
Corrections Issued 1/25/2022 KHEDER ALRAZAA
Quality Review Completed 2/1/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 2/4/2022 APPLICANT
Applicant returned to address corrections 2/15/2022 KHEDER ALRAZAA
Applicant returned to address corrections 3/10/2022 KHEDER ALRAZAA
Plan Check Approved 6/17/2022 KHEDER ALRAZAA
Issued 6/23/2022 APPLICANT
CofO in Progress 1/2/2025 MICHAEL ALLEN
Permit Finaled 1/2/2025 RICHARD STEINBACH
CofO Issued 1/2/2025 RICHARD STEINBACH
Permit Finaled 1/2/2025 RICHARD STEINBACH

Permit Application Clearance Information

Tenant Habitability Plan Cleared 3/8/2022 RICARDO BOHORQUEZ
Sewer availability Cleared 4/6/2022 JENSON LEE
Eng Process Fee Ord 176,300 Cleared 5/20/2022 JENSON LEE
Roof/Waste drainage to street Cleared 5/20/2022 JENSON LEE
Coastal Zone Cleared 6/16/2022 NOAH MCCOY
Specific Plan Cleared 6/16/2022 NOAH MCCOY

Contact Information

Architect Thomas,, Leslie; Lic. No.: C26651 1074 W TAYLOR STREET #113      CHICAGO, IL 60607
Contractor Pacific Planners & Builders; Lic. No.: 742999-B 8117 MANCHESTER AVENUE #346      PLAYA DEL REY, CA 90293
Engineer Paniagua,, Cristobal; Lic. No.: C72894 1538 W 92ND ST      LOS ANGELES, CA 90047

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/22/2023 Not Ready for Inspection EVAN COOPER
METHANE-Barrier 2/22/2023 Not Ready for Inspection EVAN COOPER
METHANE-Subgrade 2/22/2023 Not Ready for Inspection EVAN COOPER
Footing/Foundation/Slab 4/17/2023 Corrections Issued EVAN COOPER
METHANE-Barrier 4/17/2023 Approved EVAN COOPER
METHANE-Subgrade 4/17/2023 Approved EVAN COOPER
Footing/Foundation/Slab 6/15/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 7/31/2023 Partial Approval KENNETH NAGLE
Shower Pan 7/31/2023 Approved KENNETH NAGLE
PLUMBING-Rough 8/8/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 8/10/2023 Approved EVAN COOPER
PLUMBING-Rough 8/10/2023 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 8/15/2023 Corrections Issued HERBERT GIRON
Green Building Rough 8/15/2023 Not Ready for Inspection HERBERT GIRON
HVAC-Rough 8/15/2023 Conditional Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 8/24/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 8/29/2023 Corrections Issued HERBERT GIRON
Green Building Rough 8/29/2023 Not Ready for Inspection HERBERT GIRON
BUILDING-Rough-Frame 9/1/2023 Conditional Approval HERBERT GIRON
Green Building Rough 9/1/2023 Approved HERBERT GIRON
Interior/Exterior Lathing 9/1/2023 Approved HERBERT GIRON
Insulation 9/7/2023 Approved HERBERT GIRON
Drywall Nailing 9/25/2023 Partial Approval HERBERT GIRON
Drywall Nailing 10/10/2023 Approved HERBERT GIRON
HVAC-Final 11/13/2024 Corrections Issued HERBERT GIRON
PLUMBING-Final 11/13/2024 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 12/2/2024 Corrections Issued BOBBY KEY
PLUMBING-Final 12/2/2024 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Final 12/10/2024 Not Ready for Inspection HERBERT GIRON
HVAC-Final 12/10/2024 Not Ready for Inspection HERBERT GIRON
PLUMBING-Final 12/10/2024 Approved HERBERT GIRON
BUILDING-Rough-Frame 12/27/2024 Approved MICHAEL ALLEN
ELECTRICAL-Final 12/27/2024 Approved MICHAEL ALLEN
Final 12/27/2024 Conditional Approval MICHAEL ALLEN
Green Building Final 12/27/2024 Approved MICHAEL ALLEN
HVAC-Final 12/27/2024 Approved MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 12/27/2024 SGSOV Approved MICHAEL ALLEN
Smoke Detectors 12/27/2024 Approved MICHAEL ALLEN
Structural Steel Frame 12/27/2024 Approved MICHAEL ALLEN
Final 12/31/2024 OK to Issue CofO MICHAEL ALLEN