4231 W 59TH PL 90043

Certificate Information: 4231 W 59TH PL 90043

Application / Permit
21014-10000-06249
Plan Check / Job No.
B21LA23456
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE (297 SF.) AND ADD 386 SF. TO CREATE AN ACCESSORY DWELLING UNIT, 683 SF. PER LAMC 12.22 A.33(c),(d) AND (g) AND 65852.2(e)(1)(B).
Permit Issued
Issued on 1/18/2024
Issuing Office
South Los Angeles
Current Status
CofO Issued on 5/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/4/2022 APPLICANT
Assigned to Plan Check Engineer 1/11/2022 STANLEY RAAP
Corrections Issued 1/14/2022 STANLEY RAAP
Building Plans Picked Up 3/11/2022 APPLICANT
Applicant returned to address corrections 9/21/2023 LUKE GONZALES
Plan Check Approved 12/11/2023 WEIJIAN HUANG
Issued 1/18/2024 APPLICANT
CofO in Progress 5/2/2025 WAYNE REGESTER
Permit Finaled 5/3/2025 DEROLD HAUFF
CofO Issued 5/3/2025 DEROLD HAUFF
Permit Finaled 5/3/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/22/2022 CINDY QI
Roof/Waste drainage to street Cleared 12/22/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 1/3/2023 CINDY QI
Sewer availability Cleared 6/14/2023 CINDY QI
Public Works-Sewers Cleared 6/14/2023 CINDY QI
Public Works-Highway Ded. Cleared 6/14/2023 CINDY QI
Public Works-Open Permits Cleared 6/14/2023 CINDY QI
Grading Pre-Inspection Cleared 8/29/2023 VASIL MIHALEV
Construction near power lines Cleared 12/7/2023 EDGAR PASCUA

Contact Information

Contractor Daniels 3a2c Construction Inc; Lic. No.: 1052545-B 1245 S LABREA #124      INGLEWOOD, CA 90301

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/1/2024 Corrections Issued JOSE MACIAS
Footing/Foundation/Slab 4/1/2024 Corrections Issued JOSE MACIAS
METHANE-Barrier 4/1/2024 Approved JOSE MACIAS
METHANE-Subgrade 4/1/2024 Approved JOSE MACIAS
PLUMBING-Rough 4/1/2024 Corrections Issued JOSE MACIAS
Excavation/Setback/Form/Re-Bar 4/8/2024 Approved JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 4/8/2024 Not Ready for Inspection JOSE MACIAS
PLUMBING-Rough 4/8/2024 Approved JOSE MACIAS
BUILDING-Rough-Frame 5/3/2024 No Access for Inspection JOSE MACIAS
ELECTRICAL-Rough 5/3/2024 No Access for Inspection JOSE MACIAS
Green Building Rough 5/3/2024 No Access for Inspection JOSE MACIAS
METHANE-Rough 5/3/2024 No Access for Inspection JOSE MACIAS
PLUMBING-Rough 5/3/2024 No Access for Inspection JOSE MACIAS
METHANE-Rough 5/9/2024 Approved JOSE MACIAS
ELECTRICAL-Rough 6/7/2024 Corrections Issued JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 6/7/2024 Approved JOSE MACIAS
Green Building Rough 6/7/2024 Not Ready for Inspection JOSE MACIAS
PLUMBING-Rough 6/7/2024 Corrections Issued JOSE MACIAS
BUILDING-Rough-Frame 7/31/2024 Corrections Issued JOSE MACIAS
ELECTRICAL-Rough 7/31/2024 Approved JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 7/31/2024 Approved JOSE MACIAS
PLUMBING-Rough 7/31/2024 Approved JOSE MACIAS
Underground Mechanical 7/31/2024 Approved JOSE MACIAS
BUILDING-Rough-Frame 8/15/2024 Approved JOSE MACIAS
Green Building Rough 8/15/2024 Approved JOSE MACIAS
Interior/Exterior Lathing 8/15/2024 Approved JOSE MACIAS
Drywall Nailing 9/17/2024 Corrections Issued AMIR NAZARIAN
Insulation 9/17/2024 Corrections Issued AMIR NAZARIAN
Drywall Nailing 9/20/2024 Approved ALEX COLIN
Insulation 9/20/2024 Approved ALEX COLIN
Final 1/15/2025 Corrections Issued JOHN QUINTANILLA
Green Building Final 1/15/2025 Corrections Issued JOHN QUINTANILLA
PLUMBING-Final 1/15/2025 Approved JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 1/15/2025 SGSOV Approved JOHN QUINTANILLA
Smoke Detectors 1/15/2025 Approved JOHN QUINTANILLA
Final 1/30/2025 Conditional Approval JOHN QUINTANILLA
Footing/Foundation/Slab 1/30/2025 Approved JOHN QUINTANILLA
Green Building Final 1/30/2025 Approved JOHN QUINTANILLA
Final 3/27/2025 Corrections Issued MICHAEL LEWIS
Pre-Inspection 4/21/2025 Approved WAYNE REGESTER
Final 5/1/2025 OK to Issue CofO WAYNE REGESTER