2717 S CEILHUNT AVE 90064

Certificate Information: 2717 S CEILHUNT AVE 90064

Application / Permit
21014-10000-06233
Plan Check / Job No.
B21LA23403
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION (BEDROOM ENLARGE AND BATHROOM) AND KITCHEN REMODEL TO (E) ONE STORY SFD.
Permit Issued
Issued on 3/23/2022
Issuing Office
Current Status
CofO Issued on 9/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/15/2021 APPLICANT
Assigned to Plan Check Engineer 12/21/2021 TSE MING HUANG
Corrections Issued 12/29/2021 TSE MING HUANG
Plan Check Approved 2/10/2022 KHUONG TRUONG
Issued 3/23/2022 APPLICANT
Building Plans Picked Up 3/29/2022 APPLICANT
CofO in Progress 9/21/2022 MICHAEL PELHAM
Permit Finaled 9/24/2022 DANIEL ORRANTE
CofO Issued 9/24/2022 DANIEL ORRANTE
Permit Finaled 9/24/2022 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/27/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 1/31/2022 DINAH GARIN

Contact Information

Contractor Owner-Builder       ,
Engineer Stewart,, Carl; Lic. No.: C86681 8811 GENTLE WIND DR      CORONA, CA 92883

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/8/2022 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 4/21/2022 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 4/21/2022 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 4/28/2022 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 5/26/2022 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 5/26/2022 Partial Approval JOHNNY MIRANDA
Insulation 6/14/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 6/14/2022 Partial Approval JOHNNY MIRANDA
Drywall Nailing 6/22/2022 Approved JOHNNY MIRANDA
Final 9/12/2022 Corrections Issued JOHNNY MIRANDA
BUILDING-Rough-Frame 9/19/2022 Approved MICHAEL PELHAM
Final 9/19/2022 Not Ready for Inspection MICHAEL PELHAM
Green Building Final 9/19/2022 Approved MICHAEL PELHAM
Green Building Rough 9/19/2022 Approved MICHAEL PELHAM
HVAC-Final 9/19/2022 Approved MICHAEL PELHAM
PLUMBING-Final 9/19/2022 Approved MICHAEL PELHAM
SGSOV-Seismic Gas S/O Valve 9/19/2022 SGSOV Approved MICHAEL PELHAM
Smoke Detectors 9/19/2022 Approved MICHAEL PELHAM
Final 9/21/2022 Conditional Approval MICHAEL PELHAM